Inspection History: GRADING - FINAL
Permit Number - T03BU01928
Inspection Description - GRADING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2006 | GRADING - FINAL | Approved | FINAL GRADING APPROVED PER ERNIE DUARTE. | |
| 07/14/2006 | GRADING - FINAL | Denied | DENIED, PER MEETING W/ARCHITECH FOR PROJECT - PRIOR TO FINAL GRADING APPROVAL, COMPLETE THE FOLLOWING: 1) PROVIDE FLOW VOLUME OF NEW CHANNEL LOCATED ALONG N. SIDE OF COURTYARD. 2) ENSURE CONSTRUCTED CHANNEL DRAINS INTO PROPOSED SUMP (SHOW ELEVATIONS). 3) SIZE PUMP IN ORDER TO HANDLE FLOW FROM CHANNEL. PROVIDE SPECS OF PUMP 4) PROVIDE ADDITIONAL ELEVATIONS OF WATER HARVESTING AREA ON WEST SIDE OF COUTYARD. |
|
| 07/06/2006 | GRADING - FINAL | Correction Required | 1) PROVIDE AN APPROVED REVISED PLAN SHOWING CHANGES MADE TO THE SITE STORM WATER DRAINAGE PATTERNS - SPECIFICALLY THE CHANGES MADE TO THE SIDEWALK RAMP ON THE SE CORNER OF COURTYARD BETWEEN BLDGS 3 AND4. ALSO THE ADDED DRAINAGE CHANNEL ALONG THE COURTYARD. 2) CORRECT PROBLEMS WITH NEW DRAINAGE CHANNEL - CHANNEL DOES NOT DRAIN. 3) CORRECT THE STORM WATER OUTLET PIPE ON NW CORNER OF COURTYARD ( THE INVERT OF PIPE IS HIGHER THAN SIDE WALK IN FRONT OF BLDG #2). 4) BRING ROCK OF NEW DRAINAGE CHANNEL LEVEL WITH SURFACE OF ADJACENT SIDE WALK OR ADD A SAFETY RAILING ALL ALONG WHERE CHANNEL AND SIDE WALK MEET. |
|
| 02/16/2006 | GRADING - FINAL | Not ready for Inspection | MET WITH NEW GENERAL CONTRACTOR FOR THE SITE (ROBERT DELMASTRO), HE STATED THAT HE WOULD BE RESPONSIBLE FOR CORRECTING, REPAIRING AND FINISHING THE SITE WORK. SCHEDULED A MEETING FOR FRIDAY 2/17/06, WITH JIM FEMLING, LOREN MANKUS, THE CONTRACTOR AND ME TO WALK THE SITE AND DEVELOP A DETAILED PUNCH LIST OF ITEMS THAT WOULD BE REQUIRED TO FINISH THE SITE WORK. |