Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T03BU00727


Addresses:

3333 N WALNUT AV

Inspection Status: Approved

Inspection History: LANDSCAPE INSPECTION

Date Description Inspector Results Comments
12/02/2008 LANDSCAPE INSPECTION Approved
03/25/2008 LANDSCAPE INSPECTION Correction Required On-Site Monitoring. On-site monitoring of all aspects of site clearing, grading, plant protection, preservation, salvage, and mitigation shall be provided during project construction at the expense of the developer for all residential development that is over five (5) acres and for all commercial and industrial development that is over one (1) acre. The monitoring shall be performed by an individual who is qualified in arid lands native plant resource identification and protection as specified in Sec. 3.8.4, General Provisions and Requirements. The monitor shall provide periodic progress reports to the developer outlining the status of work accomplished and any problems encountered. A copy of these reports shall be submitted to the Development Services Department (DSD) for the project file. (Ord. No. 9392, §1, 5/22/00) Monitoring report required as to the disposition of PIP and TOS plants per approved plan.

Verify that all Engineering comments and concerns are addressed.
08/18/2004 LANDSCAPE INSPECTION Not ready for Inspection Monitoring report required within 30 days of 8/18/04
Provide irrigation to salvaged plants in a temporary holding area. Provide irrigation to PIP, TOS, and mitigation plant materials per DS 2-15.3.4.B.4 some trees that have been transplanted in the holding area are stressed or dead.
Provide protection from damage for the natural vegetation per DS 2-15.3.4.B.5. Preserves in place tress have been improperly pruned along Christopher City Wash.
All plants designated by the approved Native Plant Preservation Plan to be preserved-in-place shall be retained at their existing grade during and after construction. Preservation fencing per DS 2-06. Figure 1 is required to be installed beyond the "drip-line" of the vegetation by one-half (½) the distance of the "drip-line" radius. DS 2-15.6.A. Trenching has occurred within the Christopher City Wash inside the preservation fencing and disturbed the drip line of trees designated as preserve in place. Large mesquite tree in the northwest portion of the property designated as preserve in place has dirt covering the bottom 1/3 of the trunk.
The site developer shall include language in all contracts with contractors about the importance of staying out of all undisturbed natural desert areas and away from all individual Protected Native Plants to be preserved-in-place per DS 2-15.6.0.B
On-site monitoring of all aspects of site clearing, grading, plant protection, preservation, salvage, and mitigation shall be provided during project construction at the expense of the developer LUC 3.8.6.6B