Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/17/2005 | GRADING - FINAL | Approved | ||
| 05/10/2005 | GRADING - FINAL | Denied | SEE PREVIOUS COMMENTS. PROVIDE REVISED GRADING PLAN. | |
| 01/10/2005 | GRADING - FINAL | Denied | 1. PROVIDE A REVISED GRADING PLAN FOR REVIEW AND APPROVAL BY THE CITY OF TUCSON ENGINEERING AND ZONING DIVISIONS THAT SHOWS ALL REVISIONS AND MODIFICATIONS. SEE THE GRADING AND PAVING NOTES 8, 10 AND 14 ON PAGE 1, OF THE GRADING PLAN. 2. THE SITE PERIMETER WALL IS NOT CONSTRUCTED TO THE PLAN SPECIFICATIONS. PROVIDE A REVISED AND APPROVED PLAN. 3. PROVIDE SOIL STABILIZATION FOR LOT 6 UNTIL CONSTRUCTION OF BUILDING. 4. PROVIDE DRAINAGE OPENINGS IN THE SITE PERIMETER WALL AS SHOWN ON THE GRADING PLAN. 5. CONSTRUCT THE ROCK LINED DRAINAGE SWALE AT THE NORTHEAST AND SOUTHEAST DRAINAGE OUTLETS AS SHOW IN DETAIL A, PAGE 5. 6. CONSTRUCT THE RETENTION/DETENTION BASIN OVERFLOW PIPE INLETS AND OUTLETS PER DETAIL M, PAGE 5. 7. PROVIDE ROCK RIPRAP AT THE OUTLET ON THE EAST END OF THE RETENTION BASIN NEAR BUILDING 8. 8. COMPLETE CONSTRUCTION AND STABILIZATION OF THE RETENTION/DETENTION BASIN NORTH OF BUILDINGS 2 AND 3. 9. PROVIDE A SIDEWALK SCUPPER ON LAUREL AVENUE BETWEEN BUILDINGS 16 AND 17. SEE KEYNOTE 20, PAGE 2. 10. COMPLETE THE SIDEWALK ON THE NORTH SIDE OF BUILDING 31. 11. PROVIDE BICYCLE PARKING NEAR BUILDINGS 1, 16, 22, AND 31. 12. PROVIDE THE HANDICAP PARKING, STRIPING AND RAMP AT THE NORTHEAST CORNER OF BUILDING 32. 13. PROVIDE 6" VERTICAL CURB AT THE ENTRANCE DRIVE. SEE DETAIL E, PAGE 5. 14. STRIPE THE PEDESTRIAN WALKWAYS ACROSS THE ENTRANCE DRIVE AND BETWEEN BUILDINGS 8 AND 31. |