Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case: T02VL01584

Parcel: 130130580


Addresses:

3775 E 34TH ST


Inspection Status: Correction Required

Inspection History: INITIAL CODE VIOLATION

Case Number - T02VL01584

Inspection Description - INITIAL CODE VIOLATION

Inspection Status - Correction Required

Date Description Inspector Results Comments
08/05/2002 INITIAL CODE VIOLATION Correction Required 40'X40' SECTION OF PANELIZED ROOF COLLAPSED @ 5.55PM.TFD RESPONDED BUT FAILED TO NOTIFY DSD. BEAMS, PURLINS. SHEATHING, 2" SPRINKLER SYSTEM, ELECTRIC CIRCUITS, DUCTING ALL HEAVILY DAMAGED. OFFICE AREA FURTHER FLOODED BY BREAK IN FIRE SPRINKLER. TENANTS WOULD LIKE TCO FOR UNAFFECTED AREA OF CALL CENTER. SITE WILL NEED TO BE INSPECTED BY ELECTRICAL INSPECTOR. I WILL ALSO ASK INSPECTIONS MANAGERS STEVE LONG TO VISIT SITE IN AM. OVER LOADING OF ROOF BY RAIN WATER NORTH OFFICE AREA. BUILDING: 40' X 40' PANELIZED ROOF COLLAPSE. ELECTRIC BRANCH CIRCUITS UNDER AFFECTED AREA. PLUMBING: FIRE SPRINKLER SYSTEM IN AFFECTED AREA ROOF DRAIN IN AREA. MECHANICAL: DUCTING RUNNING THROUGH AFFECTED AREA SUMMARY PERMITS REQUIRED TO RETURN ABOVE CEILING AND ROOF AREA TO PREVIOUS CONDITION. ORIGINAL PLANS FOR PANELIZED ROOF SHOULD BE AHERED TO. FOLLOW UP 9/5/02