Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2003 | ELECTRIC - FINAL | Approved | IVRS - Inspection 0000*SENT TO TEP ON 4/09/03 AT 2:15AM | |
| 04/04/2003 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection 0000* | |
| 03/21/2003 | ELECTRIC - FINAL | Denied | IVRS - Inspection 0999* 1.) SERVICE MUST HAVE ADDRESS ON IT. 2.) EACH DISCONNECT MUST BE IDENTIFIED 3.) GROUND THE BUSHING IN THE METER ENCLOSURE AND GUTTER TO ENCLOSURE. 4.) THE PLAN SHOWS 2-3" CONDUITS WITH 3 - 350 MCM ON SITE ONLY ONE 4" CONDUIT WITH 6 350'S GET OK FROM ENGINEER. 5.) THE 3/0 COPPER FROM GROUND RODS TO GO TO A NEUTRAL CONNECTION AT METER OR GUTTER ENCLOSURE. 6.) TEP REQUIRES 2' OF CABLE AT END OF WEATHER HEAD. 7.) GROUND ALL BUSHING AT DISCONNECTS BECAUSE YOU ARE GOING THUR CONCENTRICS 8.) UNDERGROUND HAS TO BE INSPECTED. 9.) OPEN CONNECTIONS TO J-BOX. |