Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 09/10/2003 |
PLUMBING - GAS PRESSURE TEST |
|
Approved |
IVRS - Inspection 0000* |
| 09/05/2003 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) GAS PRESSURE HOLDING AT 15 POUNDS 2) 140,000 BTU WITHOUT FURNACE 40' RUN IS GOOD FOR 171 CFH, NEED BTU RATING OF FURNACE FOR CALC 3) NEED BATH FLUES WATER HEATER AND FURNACE, ALSO COMBUSTION AND RELIEF DUCTS 4) CONC. IN TUB TRAP 5) SECURE COPPER WATER INSIDE AT FRONT BEDROOM |
| 08/28/2003 |
PLUMBING - GAS PRESSURE TEST |
|
Denied |
IVRS - Inspection 0999*/1) INADEQUATE TEST ON DWV SYSTEM. 2) PAD ALL WEATHERLINES PENETRATING STEEL FRAMING. 3) SOME MECHANICAL REGISTERS NEED ADDITIONAL SUPPORT. 4) NAIL PROTECT PENETRATIONS LESS THAN 1-1/4" FROM FACE OF FRAME. 5) FINISH FRAMING AROUND WINDOWS. |