Permit: T02CM05552

Parcel: 13201001B


Addresses:

5741 E IRONWOOD ST

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
01/13/2005 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*REVISED CITY APPROVED PLAN ON SITE APPROVED
12/13/2004 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
11/19/2004 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
09/23/2004 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*/03005-SEE NOTE #1 FROM 7/19/04 INSPECTION 03075- 1 1/4 GAS PIPING FROM BUILDING UNDERGROUND TO METER LOCATION 14 PSI TEST OK.
07/19/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/ 1) 4" BLDG SEWER FROM 2-WAY CLEANOUT TO TIE IN TO 6" SEWER WATER TEST OK PENDING REVISED CITY APPROVED PLAN OF THIS INSTALLATION 2) 60 PSI AIRT TEST ON 2" COPPER FROM METER LOCATION ACROSS DRAINAGE TRANSITION TO 2" PVC SCHEDULE 40 TO BACKFLOW PROTECTION DEVICE OK PENDING CITY APPROVED REVISED PLAN SHOWING THIS INSTALLATION 3) HAVE YOUR PERMIT CARD AND APPROVED PLAN ON SITE AT ALL TIMES
05/12/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/ WTR TEST FROM BLD 2-WAY C.O. BACK INTO BLD FOR ALL UNDERSLAB WASTE AND VENT TO 2' ABOVE FINISHED FLOOR OK. CALL IN FOR INSP FOR PRE-SLAB PIPE WRAP AND TRAP PRIMERS.
05/11/2004 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*/ 1) AIR OR WTR TEST ALL PIPING. 2) PROVIDE ALL PIPING WITH AT LEAST ΒΌ" PER FOOT FILL 3) NORTH REST ROOM LAV AND FLOOR SINK DRAINAGE WILL REQUIRE FULL SIZE UPPER TERMINAL C.O. 4) INSTALL BLD SEWER PER PLAN OR HAVE REDLINES ON SITE FOR COMPARISON TO FUTURE CITY APPROVED REVISED DRAWING 5) BLD SEWER IS UNDER FOOTING OR IN IT.