Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 09/26/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 05/22/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*OK TOP OUT PERIMETER WALLS OK COL'S. |
| 05/20/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*4TH LIFT. |
| 05/16/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) 3RD LIFT, NOTE: FRONT COLUMN FOOTING WERE INSPECTED AND APPROVED |
| 05/13/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*2ND LIFT & WEST COL.S |
| 05/12/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*1ST LIFT NORTH, EAST & SOUTH WALLS. |
| 04/17/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*OK PERMETER STEM. |