Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T02CM05318

Parcel: 11628001E

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
12/29/2004 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
06/17/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/ 6" DOMESTIC WTR SERVICE FOR BLDG I AIR TEST OK.
06/14/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/ 1) 6" DOMESTIC WATER SERVICE AND 8" FIRE LINE SUPPLY IS OK BEHIND BLDG I AND J. 2) OK TO BACKFILL TRENCH 3) WILL REQUIRE A RED LINE DRAWING ON APPROVED PLAN SHOWING REFISED AS BUILTS
06/04/2004 PLUMBING - ROUGH, SOIL Partial Approval 1-E 6" WATER SUPPLY FROM 4 X 2" METER BANK TO RISER AT BLDG E LINE5.9 OK TO COVER. A) MEGA LUGS & RESTRAINTS OK. B) THRUST BLOCKS OK. C) PRESSURE TESTED TO 80 psi OK
01/06/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR 6" RAIN LEADERS BETWEEN GRIDS 33.1 AND 28 BLDG J LEVEL P1. 3) BLDG J LEVEL P-2 BALCONY AREA DRAINS AS NOTED ON PLAN.
01/05/2004 PLUMBING - ROUGH, SOIL Partial Approval 4" WASTE FROM LEVEL P3 AT QQ.1 AND 29 UP AND SPLITS THRU FLOOR OF P2 UP TO P1 WASTE AND VENT FOR URINAL AND LAVS IN MENS P267 AND FLOOR AREAS. WOMENS - P264 FLOOR DRAINS AND STUBS FOR STOOLS IN BOTH RESTROOMS BELOW FLOOR APP. MENS - P267 LAVS AND URINALS IN WALL UP TO CEILING OF P1 WASTE AND VENT WATER TEST APPROVED.
12/31/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
12/31/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) 4" WASTE RISER AT ELEVATOR 2 CORNER, CEILING OF LEVEL P2 AND CONNECTING PIPING THRU FLOOR TO REVENT HEIGHT ON LEVEL P1. 3" GREASE WASTE AT L.1 AND BETWEEN 19 AND 20 TO P-11B (ONLY) WATER TEST ON ALL THIS APPROVED THRU FLOOR ROOM 1041, 1043, 1045 AND 1047 4" WASTE RISER WITH 3" RELIEF VENT FROM LEVEL P2 UP THRU LEVEL P1 TO BE AIREATOR FITTING WATER TEST APPROVED
12/24/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR LEVEL P-1 SOIL WASTE LINES AS NOTED ON PLAN FOR UNITS 1049 AND 1051 ONLY BETWEEN GRID LINES 19.5 TO 21 AND L-1 TO M-1.
12/22/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* INSPECTION FOR MOCK UP ROOMS P2-C/1049 & 1051 3/4" CU HOT & COLD SUPPLY; STUBBED OUT INTO CORRIDOR. 90psi AIR TEST OK. 2) DRAIN SYSTEM TESTED TO LEVEL P1 OK. 3) OK TO COVER THESE 2 ROOMS ONLY.
C.O.T. NEEDS PERMITS TO CONTINUE WITH INTER INSP. PLEASE OVER SIZE ANY DRILLED SHEETROCK PENETRATIONS SO THEY MAY BE FIRE CAULKED.
12/18/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
12/16/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ SOIL WTR TEST IS OK FOR MAIN TRUNK LINE P-2 LEVEL BLDG I AS NOTED ON PLAN.
12/12/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR BLDG 'H' LEVEL P-2 BETWEEN GRIDS CC.2 TO EE AND BETWEEN #31 TO 32.1 AS NOTED ON PLAN.
12/11/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR WING J, P-1 LEVEL BETWEEN GRID #UU TO XX AND BETWEEN 25.1 TO 28 AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
12/10/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST IS OK FOR PLANTER DRAINS BETWEEN GRID 35 AND 32.2 AND KK AND QQ 2) RAIN LEADED FOR LEVEL P1 AND P2 WING I KK TO QQ
12/09/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK FOR 3-8" WASTE AND STORM DRAINS BETWEEN HH AND GG AND STUBBED OUT 5' PAST 34.2 2) GREASE WASTE LINE BETWEEN FF AND GG AND 5' PAST 32 COLUMN 3) RAIN LEADED WATER TEST IS OK FOR P-2 AND P-1 WINGS I AND J AS NOTED ON PLAN
12/08/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST FOR 6" RAIN LEADERS IN WING S LEVEL P-2 AND P-1 AS NOTED ON PLAN. 2) SOIL WTR TEST FOR 8" RAIN LEADERS AND 8" SANITARY WASTE LINES FROM GRIDS FF AND GG TO 10' PAST COLLUM #34 IS OK FOR BACKFILL AS NOTED ON PLAN.
12/05/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR BLDG H - LEVEL P-1, SANITARY WASTE BETWEEN GRID #29 TO 30 AND DD1 TO GG AND 8" STORM DRAINS BETWEEN GRIDS 31 TO 32.4 AND FF TO GG.1 ONLY. 3) OK TO BACKFILL TRENCH.
12/02/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) THIS INSPECTION IS FOR WING 'H' LEVEL P-1 U.G. SANITARY WASTE ONLY, BETWEEN GRID CC.2 TO DD.1 AND 28.3 TO 31 AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
12/01/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WTR TEST IS OK. 2) OK TO BACKFILL TRENCH. 3) THIS ISPECTION IS FOR U.G. PLBG FOR BLDG 'H' LEVEL 'P-1' BETWWEN GRID 30 TO 32 AND FF TO GG AND PARTIAL ON LAUNDRY BETWEEN CC.2 AND DD AND FROM 28 TO 29.8 ONLY.
11/25/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) SOIL WATER TEST IS OK. 2) THIS INSP IS FOR LEVEL P-2 BETWEEN GRIDS #30 & 33.1 AND FF AND GG LINE ONLY. 3) OK TO BACKFILL TRENCH.
11/14/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ SPECIAL AFTER HOURS INSPECTION ON APA ACCOUNT PER STEVE LONG. - BLDG 'H' LEVEL P1. 1) 4" GREASE WASTE FROM 27.1 TO 30 COLUMN LINE WATER TEST OK. 2) 8" RWL FROM COLUMN LINE 28 TO 34 WATER TEST OK.
11/13/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) 6" RWL UNDER MECH 112 (P2.19 REDLINE) 2) 6"->8" RWL FF/GG TO LINE 3. 3) RWL LINE GG.1 MOVED TO TRENCH LINE FF.9 OK (P2.19) 4) 4" TO 6" SANTARY WASTE RELOCATED AS RED LINE P2.19. 5) NOTE RELOCATIONS TO TRENCH LINE FF.9 RED LINE P2.19.
11/04/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR BLDG 'H', LEVEL P-1, FOR B-268, B-270 AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
11/03/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) 6" DOMESTIC WATER MAIN FOR WEST SIDE OF BLDG 'E' IS OK. 2) OK FOR BACKFILL.
10/30/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) GREASE INTERCEPTER INSTALLATION IS OK FOR HOTEL KITCHEN
10/24/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
10/22/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR BLDG A, LEVEL 1, ROOMS #3017, 3019 AND FOR BLDG E, LEVEL 1, ROOMS #3091, 3093 AND 3095 ONLY 3) OK TO BACKFILL TRENCH
10/20/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR BLDG 'E' LEVEL 1, RMS 3101,3103,3097, 3099 ONLY. 3) OK TO BACKFILL.
10/16/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK FOR BLDG 'E' LEVEL 1 RM. 3106 AND FOR BLDG 'A' LEVEL 1, RM. 3005,3007. AND BLDG 'G' LEVEL P-2 RM. P171, P190, P191, AND B112, B113, B114, B115. 2) SOIL WATER TEST IS OK FOR 6" RAIN LEADERS FOR BLDG 'E' WEST BETWEEN GRIDS P-1 EAST TO GRID 5 AND BETWEEN GRIDS 3 TO 6 AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
10/14/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR BLDG 'A' - ROOMS 3009,3011,3013,3015 ONLY. 3) OK TO BACKFILL TRENCH.
10/13/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
10/10/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST FOR RAIN LEADERS AND ROUGH SOIL IS OK FOR LEVEL P-1 BLDG 'E' BETWEEN GRID LINES # 1&2 AND S&U ONLY. 2) RAIN LEADERS FOR BLDG 'C' POOL GRILL RM P-106 IS OK AS NOTED ON PLAN.
10/08/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* / 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR ADDED FLOOR DRAINS IN STEAM P-136 AND P-173 ONLY AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
10/07/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR U.G. SOIL FOR PEDICURE ONLY AND FOR FLOOR DRAINS AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
10/06/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
10/04/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ SOIL WATER TEST IS OK FOR BLDG A LEVEL P-1 BETWEEN GRID B THRU F AND COLUMN 12 TO 14 IS OK. OK TO BACKFILL TRENCH.
10/01/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR BLDG 'C' 1ST FLOOR LEVEL, P-2 VENDING AREA. 3) OK TO BACKFILL TRENCH.
09/29/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR 4" SANITARY WASTE IN LEVEL P-2. MUST RED LINE AS BUILTS ON RELOCATION OF THIS DRAIN. 3) OK TO BACKFILL TRENCH.
09/26/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST FOR GREASE LINE AND SANITARY SYSTEM IS OK. 2) THIS INSPECTION IS FOR U.G. PLBG IN POOL KITCHEN AREA ONLY AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
09/22/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST OK. 2) THIS INSPECTION IS FOR U.G. SOIL FOR BLDG J BETWEEN GRID QQ TO VV AND FROM GRID #24.1 TO 27.3 AS NOTED. 3) OK TO BACKFILL TRENCH./ ALSO, P2.19A - 6" RWL AT 2.5 - 6" N/H WITH HUSKEE BANDS. - Y TEE AT Z 10.5 - WATER TEST OK.
09/15/2003 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection 0999*/1) UNABLE TO LOCATE
ANYONE ON THE WORK SITE. WENT TO PLUMBER'S OFFICE TRAILER. i WAS ADVISED THAT PLUMBERS LEFT AT 2:30 PM AND HE WAS UNABLE TO HELP ME. RESCHEDULE AND I WILL ATEMPT AN EARLIER INSPECTION.
09/11/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST IS OK FOR U.G. PLBG, BLDG G. 2) THIS INSPECTION IS ROUGH PLBG BETWEEN COLUMN YY TO BB AND GRID LINE 7.1 SOUTH TO TWO WAY C.O. AND AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
09/10/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK FOR BOTH 6" WASTE AND 6" RWL BETWEEN COLUMN F.1 TO COLUMN I AND BETWEEN GRID #15.1 TO 17 AS NOTED ON PLAN 2) OK TO BACKFILL TRENCH
09/09/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK FOR BLDG A P-1 LEVEL. 2) THIS INSPECTION IS FOR U.G. PLBG. FOR UNITS 2008, 2010, 2012, 2014, 2016, 2018 AND 2020. 3) 6" RAIN LEADER FOR UNITS 2010, 2012, 2014, AND 2016. WATER TEST IS OK. 4) OK TO BACKFILL TRENCH.
09/05/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS-OK 2) THIS INSPECTION IS FOR UG SOIL BLDG E FOR ROOM #2094, 2096, 2093, 2100, 2102 AND 2104 ONLY AS NOTED ON PLAN 3) OK TO BACKFILL TRENCH
09/02/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST OK. 2) THIS INSPECTION IS FOR BLDG 'E' - ROOMS 2086, 2088, 2090, 2092. ROUGH PLUMBING AND 8" SANITARY TRUNK LINE FROM COLUMN 1.5 TO COLUMN #7 AND BETWEEN GRID R&S. 3) INSPECTION FOR BLDG 'A' BETWEEN GRID C EAST TO GRID F. SANITARY AND RAIN LEADER TRUNK LINE STUBBED OUT OF BLDG ONLY. 4) OK TO BACKFILL TRENCH
08/28/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR U.G. SOIL FOR LOBBY BAR BETWEEN COLUMN #22.6 AND 22.8 AND #41 AND 43 ONLY
08/26/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR 8" RAIN LEADER BETWEEN COLUMN #22.5 TO 22.8 AND BETWEEN #41 AND #43 ONLY.
08/20/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR U.G. SOIL FOR LOBBY BAR AND CASUAL STORAGE BETWEEN GRID LINE 22.4 TO 22.5 AND BETWEEN GRID #40 TO #42. 3) OK TO BACKFILL TRENCH.
08/19/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*
08/17/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/AFTER HOURS INSPECTION FEE PAID IN FULL. CHECK # 434 - $102.00. 1) SOIL WATER TEST OK. 2) THIS INSPECTION IS FOR 6" RAIN LEADER FROM 22.2 TO 22.5 AND BETWEEN GRID #40 AND 42, AND 3" SANITARY WASTE AS NOTED ON PLAN. 3) OK TO BACKFILL TRENCH.
08/15/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR RAIN LEADERS BETWEEN GRIDS #27.5 AND 28.2 AND UU TO XX ONLY. 3) OK TO BACKFILL TRENCH.
07/15/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST OK. 2) THIS INSP. IS FOR 4" WASTE BETWEEN GRID QQ-1 EAST TO RR AND 6" RAIN LEADER BETWEEN GRID SS-1 AND EAST TO KK AND BETWEEN COLUMN #34-1 NORTH TO 32-2 AND BETWEEN COLUMN # 29 AND 28-2.
07/14/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR RAIN HEADERS BETWEEN GRID #NN AND OO AND BETWEEN COLUMN #34.1 AND 35 AS NOTED ON PLAN 3) OK TO BACKFILL TRENCH
07/11/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR FLOOR SINK AND FLOOR DRAIN IN ROOM B-104 3) WILL REQUIRE A REVISED AND APPROVED DRAWING PRIOR TO FINAL
07/10/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) SOIL WATER TEST IS OK FOR 6" RAIN LEADER BETWEEN GRID #M1 & M2 AND GRID 19 TO 17. 2) SOIL WATER TEST FOR BLDG 1 RAIN LEADERS BETWEEN GRID #JJ & QQ & 32.2 TO 35 AS NOTED ON PLAN.
07/09/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*
07/08/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) SOIL WATER TEST IS OK. 2) THIS INSPECTION IS FOR SANITARY 8" BLDG DRAIN BETWEEN GRID M-1 & M-2 AND BETWEEN COLUMN 15 TO 18 AS NOTED ON PLAN.
07/07/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*1) RAIN LEADER WATER TEST IS OK 2) THIS INSP IS FOR 8" RAIN LEADER. TRUNK LINE ONLY ONLY BETWEEN GRID #30 SOUTH TO GRID #35 AND BETWEEN GRID LL & MM. 3) OK TO BACK FILL TRENCH
07/02/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*/ 1) NOT READY FOR INSPECTION
07/01/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST FOR RAIN HEADERS IS OK BETWEEN GRID #SS AND WW AND BETWEEN GRID 32.2 SOUTH TO GRID 34.1 AS NOTED ON PLAN 2) OK TO BACKFILL TRENCH
06/30/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) RAIN HEADER WATER TEST IS OK 3) THIS INSPECTION IS FOR BLDG "B" UNITS #1038, 1040 AND FOR 6" AND 8" RWL AS NOTED ON PLAN BETWEEN GRID G EAST TO GRIDS AND BETWEEN GRID #16 SOUTH TO 18.1 4) OK TO BACKFILL TRENCH
06/27/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR UNITS 1034, 1036 BLDG "B" ONLY 3) OK TO BACKFILL TRENCH
06/25/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) SOIL WATER TEST IS OK FOR 6" WASTE BETWEEN GRID M-1 AND M-2 AND 19 TO 18.1 2) OK TO BACKFILL TRENCH
06/23/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) 4" GREASE WASTE FROM GRID K-1 EAST O-1 AND BETWEEN #GRID 18 AND 19 2) 3" SANITARY WASTE FROM M-2 TO O-1 AND UG SOIL FOR ROOM #1056 IS OK 3) OK TO BACKFILL TRENCH
06/19/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) SOIL WATER TEST IS OK FOR 6" GREASE LINE FROM GRD #19 & 20 AND K1 TO 0.1 2) GANG BATH #P102 & P103 IS OK
06/18/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK FOR WASTE, VENT AND RAIN HEADER AS NOTED ON PLAN 2) WASTE AND VENT OK IN ROOMS #1045, 1047, 1049, 1051 AND 1050 3) RAIN HEADER OK FROM GRID 19 SOUTH TO #22 BETWEEN M1 AND M2
06/12/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR 8" WASTE TRUNK LINE AND (8) BENCHES 5' OUT FROM TRUNK LINE AS NOTED ON PLAN
06/09/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) 6" BLDG DRAIN FOR P-2 UP TO SLEEVES AND 6" RAIN HEADER P-2 UP TO SLEEVES IS OK 2) SOIL WATER TEST IS OK 3) OK TO BACKFILL TRENCH
06/06/2003 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection 0000*1) NO READY FOR INSPECTION
06/02/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR 6" WASTE BETWEEN GRIDS 29 SOUTH TO 34.1 AND FROM RR ONLY 3) OK TO BACKFILL TRENCH
05/30/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000* 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR RAIN "LEADEES BEANCH "LINE BETWEEN GRID UU WEST TO TT IS OK 3) OK TO BACKFILL TRENCH
05/28/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) 6" UG WASTE LINE BETWEEN GRID QQ1 TO RRO AND BETWEEN GRIDS 28.2 AND 29 IS OK 2) SOIL WATER TEST IS OK
05/27/2003 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection 0000*/ 1) PLEASE GET ALL PLUMBING INSTALLATION PLANS STAMPED 2) P2.18 8" RWL AS HIGHLIGHTED ON PLAN-OK 3) WATER TEST OK 4) OK TO BACKFILL THIS AREA
05/27/2003 PLUMBING - ROUGH, SOIL Partial Approval 1) 6" RAIN HEADER SOIL WATER TEST IS OK BETWEEN GRIND LINE 28.2 TO 32.3 AND GRID LINE TT AND UU 2) OK TO BACKFILL TRENCH