Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/29/2004 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* | |
| 12/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/16/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/15/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/14/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/09/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*1) FOOTINGS OK AT EXTENDED RAMP WALLS OFF PAVILLION | |
| 12/07/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/02/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 12/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/29/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/24/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/15/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) SOG AROUND POOLS OK | |
| 11/09/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 11/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/27/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) STAIR 21 AND 22 OK TO PLACE CONCRETE | |
| 10/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/25/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/19/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) STAIR 16 OK | |
| 10/15/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :OK TO GUNITE WATER FEATURE WEST OF D | |
| 10/14/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/PADS FOR POP OUTS @ H OK | |
| 10/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/11/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/05/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 10/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 09/30/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) BLDG STAIR 16 OK TO PLACE AFTER STEP FORMS ARE PROPERLY SECURED | |
| 09/27/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/WHAT PART OF STAIR 16 IS DONE? 01015-DECK NAILING FOR ROOF OVER AREA F OK |
|
| 09/23/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 09/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) STAIR 23 S.O.D. OK | |
| 09/15/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 09/14/2004 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
| 09/09/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 09/08/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 09/02/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :P1-H CANT SLABEK WHEN REPAIR DOWELS EXPOXIED IN STAIR 33 SOUTH SIDE OK TO PLACE |
|
| 09/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/31/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) TOP 1/2 OF NORTH SIDE OF STAIR 33 OK | |
| 08/30/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/25/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/24/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/18/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) P2/I STAIR 25 OK | |
| 08/17/2004 | BUILDING PRE-SLAB | Denied | IVRS - Inspection : See detailed listing on site.| 999*/DENIED-REINFORCING WHERE EXPOSED TO WEATHER REQUIRES 1 1/2' AT CONCRETE COVER. 01010-AREA F COLUMN BASED NOT READY FORM? UP BEFORE RE-CALLING |
|
| 08/16/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) STAIR 10 OK 2) STAIR 19 CHAIROVER WALLS AND LEADING OK TO POUR | |
| 08/13/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 08/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*1)P2-P1/H STAIR 25 OK 2)P2-P1/C STAIR 3 OK |
|
| 08/02/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :P1-H STAIR 19 TO FIRST LANDING OK | |
| 07/30/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) 1-D PROVIDE RFI FOR MODIFICATION TO DETAIL 259 AT STAIR 10 | |
| 07/29/2004 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
| 07/27/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 07/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :SOG AT LOADING DOCK OK PLEASE CLEAN UP LOOSE RUBBLE BY CURB | |
| 07/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :P-1/D STAIR 10 NL 1/2 OK P2-H LOADING DOCK SOG SW & NE QUADRANTS OK TO PLACE |
|
| 07/21/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 07/20/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 07/15/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*1/4 SECTION AT LOADING AREA 3.0.6.(?) OK. | |
| 07/14/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 07/13/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/29/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/18/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/17/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/14/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/11/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* AREA F : P1 & 1 OK TO PLACE CONCRETE (3500 psi PER GSN'S) | |
| 06/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* P1 & 1 BRIDGE PROGRESS OK, WWF REQUIRED BEFORE POURING CONCRETE. | |
| 06/09/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) P2 AND P1-J S.O.G. FOR BATTER WALLS OK | |
| 06/08/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 06/04/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 1) P1-D CLOSURE POUR OK TO PLACE @ LINEN CHUTE WHEN SPEC INSP CONFIRMS EPOXIED DOWEL. 2) 1-G REPAIR @ ELEVATOR SHAFT OK | |
| 06/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/28/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/27/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/25/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/24/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) 1-G HOW ARE YOU GOING TO FIX ENLARGED AREA BY ELEVATOR ? RFI #776 | |
| 05/20/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/19/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) R-7 POUR BACK OK | |
| 05/13/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :*/ 1) P1-H MECH/ELECTRIC PADS WITH TURN DOWN 80 PERCENT COMPLETE. SPECIAL INSP MAY CONFIRM FINAL STEEL PLACEMENT. OK TO POUR IF SPECIAL INSP CONFIRMS | |
| 05/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* POUR BACKS OK @ P1-D | |
| 05/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 05/03/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 04/29/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 04/23/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* 6-G MILD REINFORCED SLAB OK TO PLACE A) DON'T FORGET EMBED FOR T.S. COL BELOW | |
| 04/22/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
| 04/21/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 5- H PT DECK MAKE MINOR ADJUSTMENTS TO CABLES AS NOTED. OK TO PLACE CONCRETE. | |
| 04/20/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 5-H PT DECK 95% COMPLETE FINAL INSP REQ TOMORROW | |
| 04/19/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-D SLAB INSPECTED SAT BY SPEC INSP OK EXCEPT: A) WEITZ ADDED A 4' X4' PAD THAT RE REBAR @ ZZ6.5/43. B) NO FOOTING PUT IN PER DETAIL 106. C) NO KEYWAY @ CLOSURE PER DETAIL 119. | |
| 04/16/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 1-D SOG WEST SIDE OK. 2) 1-D STAIR 9 & 11 OK. 3) P1-D SOG EAST SIDE OK WHEN SPEC INSP CONFIRMS REENTRY STEET @ CORNERS & EXPANSION JOINTS. | |
| 04/14/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 5-G PT DECK OK TO POUR. A) PROVIDE CLARIFICATION AS TO WHETHER OR NOT JAMB STEEL IS NEEDED @ NORTH END OF SW23 @ PENT HOUSE LEVEL. | |
| 04/13/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 04/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 04/08/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-H PT SLAB OK TO PLACE | |
| 03/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-G PT DECK OK TO PLACE | |
| 03/24/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 1-H BEAM 3 OK TO POUR AFTER CONCRETE SLURRY CLEANED OFF BARS & CABLES. 2) 6-D POUR BACK OK. | |
| 03/23/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-H ELEVATED SLAB OK TO POUR. | |
| 03/22/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 5-D CLOSURE POUR BEING TAKEN OUT. IT WILL REQUIRE REINSPECTION BEFORE PLACING MORE CONCRETE. 2) CURBS VARIOUS AREAS B, C, D OK TO FORM & POUR | |
| 03/19/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 6-D CLOSURE STRIP OK. 2) 1-H PT DECK LINE 24-28.2 | |
| 03/18/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 8-D A) D-WEST ADD PERIMETER BARS AND CLEAN RUBBLE OFF DECK. B) D-EAST COMPLETE TOP MAT & PERIMETER BARS. OK TO PLACE WHEN SPEC INSP CONFIRMS. | |
| 03/17/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 03/16/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 03/12/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 6-E POST TENSION SLAB OK TO PLACE a) PLEASE CHAIR STEEL OFF DECK AS INDICATED DURING INSP. b) SPEC INSP MAY CONFIRM. | |
| 03/11/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 03/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PT DECKS OK TO POUR | |
| 03/06/2004 | BUILDING PRE-SLAB | Partial Approval | AFTER HOURS INSP: 7-D POST TENSION DECK, OK TO POUR | |
| 03/05/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 2-H POST TENSION DECK CC-II OK TO PLACE WHEN SPEC INSP CONFIRMS CORRECTIONS AS NOTED @ SITE WITH SUPERINTENDDENT. | |
| 03/03/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 03/01/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* I-H CLOSURE POUR OK | |
| 02/27/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*S-E PT DECK OK TO PLACE. | |
| 02/26/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 02/24/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PT SLAB WEST OF LINE ZZ.4.5 OK TO PLACE WHEN SPEC INSP CONFIRMS CORRECTIONS AS DISCUSSED WITH JD STEEL. | |
| 02/23/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 02/18/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 02/17/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 3-B CLOSURE POUR OK. 2) 4-B, 4-D CLOSURE POUR OK. 3) 6-D POST TENSION SLAB ZZ.4.5->LINE 7 OK | |
| 02/11/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-B CLOSURE STRIP- STEEL OK BUT YOU MAY NOT POUR STRIP UNTIL PT DECK HAS BEEN SIGNED OFF BY ENG OF RECORD. 2-G PT DECK OK. 4-D PT DECK OK |
|
| 02/10/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 2-G PT DECK: MAKE CORRECTIONS AS DISCUSSED WITH DAVE & LAWRENCE AT JD STEEL. A) COMPLETE SHEAR HEADS. B) MAINTAIN CLEARANCE UNDER DEPRESSED EDGE FORM. C) MAINTAIN 3/4 CLEAR FROM DECK. D) ADD STEEL BB2/SW 24 & MAT @ BB/7.1 | |
| 02/09/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PRELIMINARY INSP OF PT DECK-> POUR CONCRETE FOR TONIGHT DUE TO DESIGN CHANGE | |
| 02/05/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1-I WEST MEZZANINE SLAB ON STEEL DECK. BLOCK OUT S END @ STAIR. PM6-B PT DECK OK TO POUR. |
|
| 02/03/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 02/02/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 6-D PRELIM INSP FOR PT DECK. PLEASE PROVIDE XTRA REINFORCEING @ FENETRATIONS AS DISCUSSED W/ STEVE & JOE MUNOZ & J D STEEL./ PM 6-D PT DECK LINE 18.1 TO LINE ZZ.4.5, OK TO PLACE. AFTER HOURS. |
|
| 01/29/2004 | BUILDING PRE-SLAB | Partial Approval | 1-H DECK POUR OK. 5-A RESCHEDULED FOR TONIGHT. | |
| 01/28/2004 | BUILDING PRE-SLAB | Partial Approval | 5-A PT SLAB OK TO PLACE. (CABLE DETAIL @16.1/F SHOWS UNIFORM TENDON 3' SHORTER . AS BUILT IS 3' LONGER THAN STANDARD. ACTUAL LENGHT NEEDS TO BE MEASURED & RECORDED SO THAT ELONGATION RECORDS WILL BE CORRECT.) 1-H PT SLAB SOUTH OF LINE 28.2 OK TO POUR. |
|
| 01/27/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 1-H PT SLAB & BEAMS- PRELIMNARY INSP LINE 28.2-LINE31. BEAM 1 LINE 28.4 1) #9 BARS OUTSIDE OF CENTER STIRRUPS NOT 6" O.C. PER DETAIL 240 2) #9 BARS INSIDE OF CENTER STIRRUPS ARE NOT SPACED MIN OF 1 BAR DIAMETER PER ACI 318. 3) #9 TOP BARS WEST OF GG ARE ONLY EXTENED 7' INSTEAD OF 8' NOTED ON PLAN. 4) #6 TOP BARS WEST OF GG ONLY HAVE 32" LAP WITH #9'S INSTAEAD OF 42" LISTED ON PLAN. 5) ALL TOP BARS TO BE TIED UP SECURELY @ENDS. 6) CITY PLAN FOR BEAM WEST OF PP.1 DOES NOT MATCH AS-BUILT. DO YOU HAVE RFI? | |
| 01/26/2004 | BUILDING PRE-SLAB | Partial Approval | 1-H prelim on pt slab A) mech embeds need to be removed in several LOCATIONS. b) PROVIDE RFI FOR SHEAR HEAD LOCATED OFF CENTER. | |
| 01/23/2004 | BUILDING PRE-SLAB | Partial Approval | 5-D- PRELIMINARY INSP OF PT SLAB PM-5-D POST TENSION SLAB ZZ.4.5-LINE 7 OK TO PLACE. |
|
| 01/20/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 5-D CHECK NE CORNER OF PT DECK FOR POSSIBLE SLAB CURD. 2) 1-H EMBEDS FOR MECH HANGERS ARE INTERFERING WITH PT CABLE ELEVATORS. EMBEDS WILL NEED TO BE REMOVED @ COLUMN LINES AS NECESSARE. | |
| 01/19/2004 | BUILDING PRE-SLAB | Partial Approval | 5-B PT SLAB OK TO PLACE WHEN SPEC INSP CONFIRM FINAL CHAIRING & CABLE PLACEMENT.(AFTER HOURS INSP) | |
| 01/15/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 5-C PT SLAB OK TO PLACE. 2) 5-B PROVIDE RFI FOR CORBEL TOO HIGH @ K/16. 3)4-D SPALLED AREAS MUST BE REPAIRED BEFORE TENSIONING | |
| 01/13/2004 | BUILDING PRE-SLAB | Partial Approval | 5-D P.T. SLAB LINE 18- LINE ZZ.4.5 A) IT IS CRITICAL THAT CENTER OF CABLE BE AT CENTER OF GRAVITY FOR CONCRETE @ ENDS. ALONG SW6 CABLE ANCHORS NEED TO BE MOVED TO CENTER OF CONCRETE. OK TO PLACE WHEN CONFIRMED BY SPEC INSP | |
| 01/09/2004 | BUILDING PRE-SLAB | Partial Approval | 4-A PT DECK OK TO POUR PM- P1-J SOG VV.1-XX OK . MECH PADS ON MEZZANINE OK. MECH PAD WEST OF VV.1 LINE OK |
|
| 01/08/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 4-A a) REINFORCE AROUND PENETRATIONS. b) INSTALL BARS @ RE-ENTRY CORNERS AND OUTSIDE CORNER @ B/14. c) INSTALL EMBEDS FORS TUBE STEEL @ STAIR LANDING. d) INSSTALL SPLAY BARS ON NORTH SIDE OF SW2 AND @ OPENING OF SW3. e) CHECK FINAL CLEARANCES. | |
| 01/07/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1-G WHERE'S RFI FOR POP OUTS ON LINE 7? | |
| 01/06/2004 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-d pt slab zz.4.5 to line 7 1) chair #4 per 12/203 @ columns. 2) chair #3 hair pins as necessary. 3) ok to place when final chair confirmed by spec insp | |
| 01/02/2004 | BUILDING PRE-SLAB | Partial Approval | 1) 1-G PT DECK OK TO POUR. 2) P1-J SOG OFF LINE 24 OK WITH MECH PADS BLOCKED OUT. (AFTER HOURS INSP.) | |
| 12/31/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PRE INSPECTION PERFORMED WITH PAUL OF DECK 1-G | |
| 12/30/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-J S.O.G. a) MILD REINFORCING OK. b) MECH PADS PER 128 NOT YET FORMED. C) BLOCK OUT COLS PER 117 | |
| 12/29/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/26/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/24/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-E PT SLAB OK TO POUR WHEN SPEC INSP CONFIRMS FINAL CABLE PLACEMENT AND THE FEW MISSED PERIMETER BARS. | |
| 12/23/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-E PT DECK CHAIR STEEL, ADD REINFORCEMENT AND ADD HAIR PINS AS INDICATED, WILL REINSPEC 12/24 | |
| 12/22/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/19/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-B PT SLAB OK TO POUR. | |
| 12/17/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) P1-H S.O.C. CC.1-EE/ 28.4-33.5 A) HAVE SPEC INSP CONFIRM FINAL CHAIRING AN DBLOCK OUT OF DRAIN TROUGH. B) what about cantilever over mech? 2) 4-C PT SLAB OK TO POUR. | |
| 12/16/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/15/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-I CLOSURE POURS AT COLS OK TO PLACE. | |
| 12/12/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 4-D PT SLAB LINE 18 - LINE ZZ.4.5 PRELININARY STEEL INSP OK. NEED TO DO FINAL INSP FOR PENETRATION REINFORCEMENT AND FINAL CHAIRING OF CABLES & BOTTOM REBAR. PM- 1) 4-D PT SLAB LINE 18 - ZZ.4.4 OK TO POUR. 2) 1-I,J COMPOSITE DECK FOR MECH MEZZANINE OK TO POUR CONCRETE |
|
| 12/11/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/08/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-A PT SLAB OK TO PLACE WHEN SPEC INSP COMPLETES FINAL P-T CABLE INSP ( ADDED HAIR PINS). | |
| 12/05/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/04/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-D PT SLAB ZZ-4.5 - ZZ.8 AND 7-10.1 OK TO POUR I HAVE SERIOUS CONCERNS ABOUT THE LACK OF SHOWING FROM LEVEL 2 TO LEVEL 3 IN AREA B, C, D. THE NORMAL CONSTRUCTION ON LEVEL 3 IS INTRODUCING EXTENSIVE POINT LOADS ONTO A DECK THAT IS STILL PARTIALLY "GREEN". PLESAE CONSULT YOUR ENGINEER AND YOUR G.S.N.'S ABOUT CONTINUOUS SHORING DURING CONSTRUCTION. IF ENGINEER OF RECORD IS GOING TO ALLOW ANY DESHORING OR CONSTRUCTION WORK ABOVE DESHORED LEVELS OTHER THAN AS SPECIFIED IN GSN'S, THEN I WOULD LIKE WRITTEN DOCUMENTATION. |
|
| 12/03/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 12/02/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-H 50G LINE 28.4 - LINE 25 OK TO POUR AFTER HOURS- P1-G PT SLAB V-Z OK TO PLACE CONCRETE WHEN SPEN INSP CONFIRMS FINAL CHAIRING AT CABLES. |
|
| 12/01/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 11/26/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 11/25/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AFTER HOURS: 2-E PT SLAB COMPLETE OK TO POUR. | |
| 11/21/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-B PT SLAB OK WHEN a) SPEC INSP CONFIRMS PROPER TENDON DRAPE @ BLOCK OUTS. b) PROVIDE RFI FOR CORBEL 1" HIGH. | |
| 11/20/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 3-B SLAB INSP DELAYED TILL TOMORROW | |
| 11/19/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*1) P1-H DD.1-FF.5 LOADING DOCK SLAB OK TO POUR. 2) 3-D LINES K & LINE 18 THRU ZZ.45 OK TO POUR | |
| 11/14/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) 2-A a) COMPLETE DETAIL S @ SW1 & SW2. b)#5 CONT. PER 210 @ SW1. c) USE 208 FOR RE-ENTRY CORNERS @ C/11 & STAIR WAY.d)#5 20' T & 13' B TO EXTEND INTO CLOSURE POUR @14/F.1. e) EXTEND 14' HST & 8' #5 B ALL THE WAY TO SOUTH END AT CLOSURE POUR. f) COMPLETE EXTRA REINFORCEMENT AT PENETRATIONS. | |
| 11/13/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 11/12/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*AM 1) 2-D PT SLAB 7-10/U-ZZ.6 OK TO POUR PM P2-C SLAB ON GRADE 0-0.3 AND INFILL @ ELEVATOR SHAFT OK. |
|
| 11/11/2003 | BUILDING PRE-SLAB | Partial Approval | 2-D PT SLAB ZZ 6.5/P-U/7-10 A) INSTALL REINFORCEING PER 208 @ ZZ.7/41-42. B) INSTALL PER 208 @ T.5/10 & U/9.5. C) ADD REINFORCING LINE 7 SOUTH SE15 & SW 16 | |
| 11/10/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM 1) 3-C PT SLAB a) INSTAL SMOOTH DOWELS PER 225 @ SW6. b) ADD SLIP SHEET @ CORNER. c) INSTALL #5 DIAGONALS PER 208 AT REENTRY CORNERS. d) PROVIDE RFI FOR CHANGE TO CAP HEAD. e) 12' #5 HOOK BARS @ ALL POP OUT EDGES. f) #5 CONT PER 210 @ SW7. g) MISSING 1 - 12' #5 LINE L, 21-22. h) ADD 12' #5 HOOK AS NECESSARY ON LINE 22 FOR 12" OC MAX. i) MISSING /35 12' LONG PER S @ SW8. j) DETAIL R SW8, SW9; EXTEND #5'S 6' INTO SLAB. k) 15' #5 REG @0/19. 2) P1-G PT SLAB. a) PROVIDE RFI FOR PENETRATIONS @ CAP HEADS AA/7.1 & 10 AND BB/10. b) SLAB DOWELS PER 210/216 @ SW23 REQUIRED. c) FINISH DETAIL R @ SW23 SOUTHEND.d) SHEAR HEAD @ AA/8. e) FINISH HAIR PINS @ ANCHORS. f) RAISE ALL REINFORCING @ CAP HEADS 3/4" FROM DECK. g) COMPLETE ALL PENETRATION REINFORCEMENT & REENTRY CORNER REINF. h) 12' HOOK BARS 16" OC ALONG SOUTH EDGE. i) BB/9 REQUIRES 2 MORE HOOK BARS. j) DETAIL 210 FOR SE24. PM 1) 3-C PT SLAB K-O/18-22, OK TO POUR. 2) P1-G PT SLAB Z.2/7.1-10 TO CC.1/30-34 OK TO POUR. |
|
| 11/07/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1-E SOG P-R/2-7 OK. | |
| 11/06/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 11/05/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 11/04/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*1) ESCALATOR PIT 50 D NOT READY. 2) CLOSURE POUR 24/JJ NOT READY | |
| 11/03/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) I-D MISSING CLOSURE POUR DOWELLS @ 41.5/ZZ.4.5. 2) 1-D, E HAVE ENG LOOK AT A CRACK IN SLAB FROM CORNER R/6.5 TOWARD 5/7 | |
| 10/31/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 10/30/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1-A SOG: A) ADD REBAR PER 147 AT WEST END. B) BLOCK OUT FOR COL AT B/15.1 C) MOVE HORIZONTAL ALONG LID 6 TO INSIDE CORNER AT SLAB DOWELS. D) OK TO POUR WHEN SP. INSP. CONFIRMS. | |
| 10/29/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) 2-B PT SLAB A) ADD EXPANSION MATERIAL PER 224 @ L/18.2 B) ADD EXTRA #5 REINFORCMENT @ F.1/18.2 FOR UNSUPPORTED CORNER (PER 5. SLONGKER) C) COLUMN HEAD DETAIL 6 CALLS FOR STEEL TO EXTEND INTO CLOSURE POUR. PROVIDE RFI MOVING IT OUT OF CLOSURE POUR OR INSTALL PER PLAN. D) OK TO POUR WHEN SPECIAL INSPECTOR CONFIRMS ITEMS ABOVE. 2) 1-D STAIR 11 A) RECONFIGURE WEST END OF NORTH BEAM FOR EQUEL CLEARANCE BETWEEN BOTTOM BARS. B) PROVIDE PROPER CLEARANCE AT SOUTH END OF WEST BEAM. | |
| 10/28/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 10/27/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PM- 1) I-E EXTRA REINFORCING FOR TUB RELOCATE. 2) P2-G SLAB ON GRADE POURED. | |
| 10/24/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1-D PT SLAB L-O/14.1-18. a) ADD 1 EACH 12' #5 PARALLED TO SW10 & SW11 PER HEX R. b) ADD 3 EACH 30' #5 AT TOP FRONT OF ELEVATOR SHAFT. c) SHEAR HEAD REQUIRED 16.5/N.5. JOE MUNOZ MAY CONFIRM ABOVE FOR SATURDAY POUR | |
| 10/23/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM 1-E PT SLAB R-U/1-7 PM P1-J SOUTH & WEST SLAB SLAB ON DECK OK TO POUR, |
|
| 10/22/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-J SLAB ON PRECAST. a) PLACE BARS FOR CANT. LEVER ON SOUTH SIDE. b) FINISH PLACING CORD STEEL ON PERIMETER. c) FINISH "Z" BARS FOR DEPRESSED SLAB. | |
| 10/20/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 10/17/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 10/16/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) P2-J A) SLAB INFILL AT 35/PP & KK OK. B) SLAB INFILL AT QQ/30 OK WHEN 3 #5 ON EAST SIDE STRAIGHTENED OUT. C) SLAB INFILL ON EAST END OF J REQUIRES 5 #6 ALONG NORTH EDGE AND THE ADDITION OF 1 #6 ON SOUTHEDGE. 2) a) SLAB IN FILL BY ELEVATOR REQIRES CLEAN UP & COMPACTION OF D.G. | |
| 10/14/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-G SOG V-AA AND AA/7.1-8 OK | |
| 10/13/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 10/10/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*STAIR 19 NOT READY. A)1 BAR DIAMETER SPACING REQUIRED BETWEEN ADJACENT BEAM BARS. B) TOP MOST & BOTTOM MOST MAT BARS ARE REVERSED. C) STIRRUPS NOT COMPLETE. PM-1) I-A PT SLAB OK I NEED RFI CONCERNING COL HEAD M @ B/14. 20 I-B PT SLAB OK TO POUR. 3) 2,1-D STAIR #9 BEAMS & MATS FOR LANDINGS OK- STEPS NOT YET FORMED OUT. OK TO PLACE CONCRETE. |
|
| 10/09/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM- I-B PT SLAB REQUIRES MINOR ADJUSTMENTS. CONTR MAKING CORRECTION AT THIS TIME. PM- 1-B F.1-K/14-18.2 A) MAKE ADJUSTMENTS @ SE CORNER TO BRING HAIR PINS DOWN TO 6 1/4" MAX HEIGHT. B) PROVIDE RFI CONCERNING "FLOATING" SECTION OF SLAB @ F.1/ 18.1. |
|
| 10/07/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-J QQ-ZZ/27.3-29 | |
| 10/06/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-I SOG OK | |
| 10/03/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-I SOG JJ-QQ/24-29.2 | |
| 10/02/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 2-C PT SLAB K-0/18-22 | |
| 09/29/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/1) P1-E SOG R-U/24.1 NOT READY A) DETAIL 102. B) PLBG WRAP. 1) P1-J S.O.D. QQ-XX.5/27.3-32.2-OK | |
| 09/26/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/P1-E MILD REINFORCED SLAB AT ELEVATOR OK. | |
| 09/25/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-A B-F/13-15.1 OK. 2) P1-I STAIR LANDINGS @ OO * KK OK | |
| 09/23/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM- 1) P1-A SOG B-I/13-16 a) FINISH COMPACTING. b) PLACE HORIZONTALS @ TURN DOWNS ALONG LINE 16. 2) P1-H, I GG/24.1-30 TO LL/24-30. a) EXTRA REINFORCEING @ GAPS IN PRECAST REQUIRES BARS T&B. b) "HOOK" BARS NEED TO BE PLACED AT SLAB DEPRESSION. c)"NEW" SLAB DEPRESSIONS AREA H (29-30) NEED TO BE BLOCKED OUT. PM- P1-H, I 24-30/ GG-LL OK |
|
| 09/22/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-A,B SOG E-K/13-16. OK TO POUR WHEN SPEC INSP CONFIRMS EPOXY DOWEL PLACEMENT ON LINE K AND FINAL POSITIONING OF WALL TO SLAB DOWELS ALONG LINE16.5 | |
| 09/17/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/1) P3-J A) FINISH COMPACTION; B) CLEAR AREA AROUND PRECAST COLS; C) NEED TO DIG OUT FOR THICKENED SLAB LINE RR & 31.1; 2) P2-I GG-KK/24-31 EXCLUDING MILD REINFORCED AREA OK TO POUR. |
|
| 09/15/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM) SLAB ON GRADE ZZ.5-ZZ.8/ 40-43 PM) P3-I OK TO POUR |
|
| 09/11/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) I-C,D P-T SLAB L/19 TO N/19 NORTH TO ZZ4.5/40-42. 2) P1-D SLAB WITH P-T BEAM T-U/8.1-10.1 (AN AFTER HOUR INSP FEE WILL BE DEDUCTED FROM YOUR ACCOUNT) |
|
| 09/10/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 09/09/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* LL-QQ/24-30 OK PM) P2-I 32-35/II.5-JJ.1 |
|
| 09/08/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1_I NOT READY. POUR PUSHED BACK TO THURSDAY. | |
| 09/05/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1-D ZZ.4/41.5-42 WITH PT BEAM A OK TO POUR | |
| 09/03/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-I JJ-QQ/30-34.9 | |
| 09/02/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* NOT READY a) STEEL NOT COMPLETE | |
| 08/29/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 08/28/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-D S.O.G. ZZ.2-ZZ.4/40-42 OK TO PLACE. | |
| 08/25/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* AM P1-I PRELIMINARY INSPECTION OF WELDS JJ-QQ OK. I NEED TO SEE SPEC INSP PM 1-C PT DECK 18.1-22/K-O OK TO POUR |
|
| 08/22/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-J QQ-YY/28.5-33 ( LESS BLOCKED OUT AREA FOR STAIR & ELEVATOR) OK TO POUR | |
| 08/21/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-I 1) SMOOTH DOWELS IMPROPERLY DURING POUR. AN RFI MAY BE NEEDED FOR REPAIR DEPENDING ON QUANTITY OF IMPROPERLY PLACED DOWELS. | |
| 08/20/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) PLEASE PROVIDE COPY OF ENGINEERS RESPONSE TO CRACK IN PT SLAB EXTENDING 2' EAST OF SW6 ON LEVEL 1. 2) progress noted on precast assembly areas I & J COMPLETE WELD REPORTS NOT YET RECIEVED. (Z 95% COMPLETE LEVEL P2 PER AVAILABLE REPORT FROM G. DAVRZIO) PM- P2-I SLAB PRECAST JJ-QQ/29.8-35 a) SMOOTH DOWELS REQUIRED 16" O C ALONG LINE 29.8 |
|
| 08/19/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P2-D T-U/7.1-10.1 SLAB ON GRADE OK WHEN SPEC INSP CONFIRMS FIBER EXPANSION JOINT AT WALLS AND SLAB DOWELLS @ ELEV. | |
| 08/11/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-D P.T. SLAB DETAIL DIDN'T ASSIGN # TO N-S TENDONS. WE WILL CALL EDGE AT SLAB TENDONS SS a,b AND THE NEXT 2 WILL BE SS d,e. | |
| 08/07/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-D PT SLAB FROM YESTERDAY'S NOTES COMPLETED & PLACED | |
| 08/06/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 08/05/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) P1-D PT SLAB AROUND ELEVATOR AREA NOT READY a) NEWLY DESIGNED DEPRESSED SLAB AREA INCOMPLETE. b) TOP MAT OF #5 12" EACHWAY NOT PLACED. 2) P1-C ASK ENG. ABOUT CABLE 69B IN 1ST PT DECK. | |
| 08/01/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) P2 D PRELIMINARY INSP OF STEEL IN SLAB. a) NORTH & SOUTH EDGES INCOMPLETE. b) TOP MAT BY ELEVATORS PITS NOT INSTALLED YET. c) SW12 WILL NEED TO HAVE VERTICAL STEEL INSTALLED BEFORE POUR IN ORDER TO GET COUPLINGS ON. 2) P3, P2,P1-I CONTINUED PROGRESS WITH PRECAST ASSEMBLY | |
| 07/31/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 07/29/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* 1) P1-C PT SLAB OK TO POUR. a) STEEL IN DECK OK. CLAM SHELL ADAPTATION INSTEAD OF TOP HAIR PINS AT ? 10 LOCATIONS. (DETAIL 239) OK b) 9 33 STIRRUPS INSTEAD OF 7 #5 STIRRUPS AT SHEAR REINFORCING (SSC3/239) OK'D BY ENG AS ALTERNATE. c) PT CABLING MUST BE APPROVED BY SPECIAL INSP BEFORE POUR. | |
| 07/28/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* | |
| 07/25/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* P1-C PROGRESS ON PT-SLAB. FINAL INSP TO BE 7/28 PM. 2) P3 I,J PROGRESS ON PRE CAST ASSEMBLY OK. |
|
| 07/24/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) P1-C AT SW6-SSK114-1A CALLS FOR 3/4" THREADED BOLTS EPOXIED INTO CORBEL THEN PUDDLE WELDED TO BENT PLATE. PLEASE PROVIDE ENGINEER RESPONSE ON POSSIBLE HEAT DAMAGE TO EPOXY | |
| 07/16/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) P1-B PT SLAB F-L/16-18 OK TO POUR AFTER FINAL INSPECTION BY SPECIAL INSPECTOR | |
| 07/15/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) P2-B SLAB ON GRADE LINE 19 NORTH TO ZZ.1 2) P1-B-PT SLAB ABOUT 80 PERCENT COMPLETE-WILL REQUIRE FINAL INSPECTION | |
| 07/03/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000* PI-B I.S-L/14-16 | |
| 07/02/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) P1-B, F-I.5/14-16 S.O.G. OK | |
| 06/27/2003 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection 0000* | |
| 06/26/2003 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection 0000*/ 1) P2-C, 19-22/L-P |