Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/28/2003 | PLUMBING - FINAL | Approved | IVRS - Inspection 0000* 1) THIS IS A FINAL INSPECTION. PLEASE MAKE ALL CORRECTIONS. I HAVE ASKED THREE TIMES TO SECURE EXPANSION TANK. STILL TOO LOOSE. ALL HOSE BIBS REQUIRE VACUUM BREAKERS. | |
| 03/27/2003 | PLUMBING - FINAL | Denied | IVRS - Inspection 0999* | |
| 03/24/2003 | PLUMBING - FINAL | Not ready for Inspection | 1.) EQUIPMENT NOT HOOKED UP NEED FINAL CONNECTIONS. 2.) TEMP C OF O SEE STEVE LONG 201 N STONE DEVELOPEMENT SERVICES 791-5550 EXT 147. |
|
| 03/20/2003 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000*NOT READY FOR INSPECTION. | |
| 03/18/2003 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000* 1.) PLEASE MAKE ALL FINAL CONNECTIONS BEFORE CALLING FINAL INSPECTIONS. 2.) PLUMBER STILL MAKING CONNECTIONS IN MECH RM. |
|
| 03/17/2003 | PLUMBING - FINAL | Denied | 1.) PROVIDE CERTIFICATION OF ALL BACKFLOW DEVICES 2.) MAKE ALL FINAL CONNECTIONS OR AT LEAST PROVIDE ALL CONNECTIONS UP TO RP2. 3.) INSULATION KITS ON HC LAVS. 4.) REMOVE UNION FROM ROOFTOP GAS. 5.) SUPPORT EXPANSION TANK. 6.) INDIRECT WASTE PIPING BETWEEN 5-15 FEET TO BE DIRECTLY TRAPPED. |