Permit: T02CM04588

Parcel: 14125001B


Addresses:

8133 S WILMOT RD


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T02CM04588

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
10/02/2003 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection 0000*/ 7 EACH PIPE SUPPORTS AT BOOSTER SLAB OK.
08/28/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000* BOOSTER PUMP SLAB (CONCRETE PIPE SUPPORT DOWELS TO BE EXPOXIED IN LATER)
08/27/2003 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection 0000* NEED #5 HOOKS 12"O.C. AROUND PERIMETER
08/13/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000* SHEAR KEY FOR BOOSTER OK TO POUR WHEN SPECIAL INSPECTOR CONFIRMS
07/25/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
07/24/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*/ 1) EXTERIOR FOOTING ON CONTROL BLDG-OK
06/26/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*/ 1) A-3 OK TO POUR (THIS COMPLETE RESEVOIR)
06/23/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*/ 1) A4 OK TO POUR (STAIR BLOCKED OUT)
06/18/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1) A-4 STILL NEEDS CTU DOWELS AND MINOR ADJUSTMENTS
05/30/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
05/20/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*OK WALLS NORTH & SOUTH VAULT.
05/19/2003 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection 0000*
05/09/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*EAST VAULT WALL OK.
05/08/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1. SLAB SECTION B3
A.) MISSING DOWEL ON LINE 1.9 (PLACED WHILE ON SITE)
B.) ALL LOOSE EARTH MUST BE REMOVED FROM OUTLET SECTION.
2.) EAST WALL VALVE VAULT NEAR COMPLETION. STILL NEED BARS FOR LANDING AND SOME HOOKS @ TOP OF WALL.
05/06/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*BOTTOM OF OUTLET STRUCTURE 2/15 OK
2.) COLUMNS G-1 & D-1 OK.
05/05/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*COLUMNS DONE EXCEPT C-1,D-1,A2,B2,
2.) PROGRESS ON VAULT.
05/02/2003 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection 0000*
04/28/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1. C3 PAD OK TO TO POUR.
2.) MET WITH P.E. LAURA CARTE ABOUT CLEARANCE FOR TOP BARS TO FORM IN DRAIN CALVERT. PLAN SHOWS 2" INSTALLERS HAVE UP TO 5" CLEARANCE THIS HAS BEEN OK'D BY P.E.
04/25/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) SITE VISIT TO OBSERVE PLACEMENT OF CONCRETE @ COLUMNS.
2.) STEEL BEING SET IN C-3.
04/24/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1. A-1 OK TO POUR.
2.) PLEASE COLUMN NOTES INCORRECT.
CORRECT COLS ARE: B-3 & C-3 ALREADY POURED. C-2 AND B-1 COLS ARE OK TO POUR.
04/23/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) D3 PLACEMENT OBSERVED OK
2.) A 2 OK TO POUR.
3.) CLOUMN D4 OK TO POUR.
04/22/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*B1 OK TO POUR.
2.) CD REQUIRED BETWEEN A1 & AZ CORNER BARS REQ. ON #S HORIZ @ A1 SLOPE.
04/18/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) E3 POURED
2.) DISCUSSED WITH BOB LENON OF TUCSON WATER WHAT TO WATCH FOR DURING CONCRETE PLACEMENT.
04/17/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*B4 & D4 PER SPECIAL INSPECTION REPORT OK TO POUR.
04/15/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*C4 OK TO POUR: D4 REQUIRES COLUMN BARS TO BE PLACED.
04/14/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*POURING C2 & E2 TODAY.
04/11/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*D1 COMPLETE
E2 COMPLETE.
3.) C2 REQUIRES CONST. #S TO SLOPE.
04/10/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
04/09/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) B2 & E2 OK TO POUR.
2.) D1 STILL NEEDS CTJ DOWELS AND WATER STOP.
04/08/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
1.) E1 COMPLETE.
2.) D1 & D2 STILL NEED CTJ DOWELS.
3.) B2 NEEDS CONTINOUS #S AT SLOPE LINES, DOWELS @ CTJ AND COLUMN REINFORCEMENT.
04/04/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) F2 COMPLETE
2.) E-1 STILL NEEDS CTD DOWELS LINE C AND CONTINUES #5 @ LINE 1.
04/02/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*F1 OK TO POUR.
04/01/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*F3 COMPLETE
2.) F REQUIRES CORNER BARS ON ALL #S HORIZ. UP TO FLAT SECTION.
3.) VALVE VAULT WALL WEST END 1S' OF N & S.
03/28/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1. F3 & E4
2.) OK TO POUR WHEN SPECIAL INSPECTOR OBSERVES FINAL PLACEMENT OF STEEL & EXPANSION JOINT.
3.) FINISH INSTALLING CONTINOUS BARS THROUGH LINE D.
4.) INSTALL LOWER MAT @ DRAIN GROOVE.
5.) 3" CLR TO EARTH REQUIRED FOR LOWER MAT @D-3 COLUMN.
6.) FINISH INSTALLING SYNTHETIC SPONAGE @ EXPANSION JOINT.
03/26/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*F4 OK TO POUR/PUMP BARREL FOUNDATION OK TO POUR.
03/25/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*SITE VISIT TO OBSERVE CONCRETE PLACEMENT AND GENERAL INSTALLATION OF REINFORCEMENT.
03/24/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*F5 OK TO POUR.
2.) E6 REQUIRES REINFORCEMENT ALONG NORTH EDGE PER PLAN. BARS BEING INSTALLED AT THIS TIME. OK TO POUR AFTER SPECIAL INSPECTOR APPROVES FINAL PLACEMENT.
03/21/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
1.) D6, E6 OK TO POUR.
03/20/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*D 2 & F6 OK TO POUR.
03/17/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*SLAB A-5,B5,E5.
03/13/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*
1.) #5 lap splice bars along line a have not yet been installed due to shipping eerror.
2.) ok to pour only when competion of #1 deserved by myself or special inspector.
03/12/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*PARTIAL OK TO POUR C5 RINGS ON CLOUMN TO BE INSTALLED AFTER POUR.
03/11/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 0000*HOLD POUR AREA C-5 UNTIL FURTHER INSP.
1.) PLEASE HAVE ALL COLUMNS STEEL AND CTU AND EJ DOWELS ETC IN PLACE.
2.) LAYOUT OF MAT AND SIZE OF #8 VENTS OK.
03/10/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*AREA B6 OK TO POUR
2.) BOND BREAKER COMPOUND REQUIRED ON SURFACE OF CT.J.
03/07/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) PLEASE NOTE SPECIAL INSPECTION IS IN ADDITION TO INSPECTION BY BUILDING OFFICIAL. I WOULD LIKE TO SEE FIELD REPORTS THAT IDENTIFY WHAT WAS LOOKED AT. IS ALSO NEED TO HAVE SPECIAL INSPECTION APPROVED BY DSD.
03/07/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*INSPECTED A.5-B.5/4-5
A.) SHEAR PINS NOT INSTALLED FOR EJ & CTU PER DETAIL PP 24.
B.) CENTER BULB WATER STOP REQUIRED TO BE SUPPORTED 12" OC. PER DETAILS ON PP 24.
C.) EJ & CTU'S ARE 9" WIDE WITH WATER STOP; INSTALL REINFORCEMENT SO THAT 9" IS LARGEST GAP THAT WOULD ENTAIL INSTALLATION OF BARS WITHIN 5" OF JOINT OR PROVIDE RFI FROM ENGINEER OKING DELETION.
D.) TAILS LOWERS MAT BARS REQUIRE 2" CLEAR FROM FORM @ TOPS.
03/06/2003 EXCAVATION/LAYOUT REBAR & ZON Denied IVRS - Inspection 0999*
03/04/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*TOP & SIDE SLOPE Z-A/4-5 IS LACKING CORNER BARS PER NOTE 3 PP. 8. IE. ALL SLIDE SLOPE BEND LINE CORNER BARS SHALL BE LAPPED.
ABOUT 1/2 OF THE #5 MAT BARS HAVE NOT HAD CORNER BARS INSTALLED AND NONE OF THE # 5 BARS RUNNING HORIZONTALLY UNDER #9 BARS HAVE CORNER BARS INSTALLED.
02/20/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) BOTTOM OF SUMP PIT IN VALVE VAULT OK. OK TO POUR WHEN FINAL FORM CLEARANCE OBSERVED BY SPECIAL INSPECTOR.
2.) 4' MAT (5 #7 EACH WAY) AT BOTTOM OF STAIR COLUMN IS MISSING. CONTRACTOR PLACING MAT @ THIS TIME TO BE CONFIRMED BY SPECIAL INSPECTOR.
3.) #6 DOWELS AT BOTTOM OF STAIR NOT IN PLACE IF DOWELS ARE TO BE EXPOXIED PLEASE PROVIDE RFI.
4.) BOTTOM OF VALVE VAULT OK TO POUR IF ITEMS 2 & 3 ABOVE TAKEN CARE OF. VERBAL OK FROM ENGINEER OK FOR NOW.
02/12/2003 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection 0000*1.) ATTENDED CONST. MEETING WITH CONTRACTOR & ENGINEER NEED TO CHECK ON HAVING SPECIAL INSPECTOR FOR JOB APPROVED.
2.) REBAR IN SUMP PIT 1/17 IN GENERAL COMPLIANCE CLEARANCE TO EARTH AT BOTTOM OF PIT NEEDS TO BE INCREASED.
3.) RFI TO ELIMINATE #11 @ 6" SLAB TO WALL DOWELS. NECESSARYY FOR CLEARANCE PER ACI. CONTINUOUS FLOOR TO WALLS @ 6" O.C. TO REMAIN.