Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T02CM04588
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/02/2003 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection 0000*/ 7 EACH PIPE SUPPORTS AT BOOSTER SLAB OK. | |
08/28/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* BOOSTER PUMP SLAB (CONCRETE PIPE SUPPORT DOWELS TO BE EXPOXIED IN LATER) | |
08/27/2003 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection 0000* NEED #5 HOOKS 12"O.C. AROUND PERIMETER | |
08/13/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* SHEAR KEY FOR BOOSTER OK TO POUR WHEN SPECIAL INSPECTOR CONFIRMS | |
07/25/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* | |
07/24/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*/ 1) EXTERIOR FOOTING ON CONTROL BLDG-OK | |
06/26/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*/ 1) A-3 OK TO POUR (THIS COMPLETE RESEVOIR) | |
06/23/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*/ 1) A4 OK TO POUR (STAIR BLOCKED OUT) | |
06/18/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1) A-4 STILL NEEDS CTU DOWELS AND MINOR ADJUSTMENTS | |
05/30/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* | |
05/20/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*OK WALLS NORTH & SOUTH VAULT. | |
05/19/2003 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection 0000* | |
05/09/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*EAST VAULT WALL OK. | |
05/08/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1. SLAB SECTION B3 A.) MISSING DOWEL ON LINE 1.9 (PLACED WHILE ON SITE) B.) ALL LOOSE EARTH MUST BE REMOVED FROM OUTLET SECTION. 2.) EAST WALL VALVE VAULT NEAR COMPLETION. STILL NEED BARS FOR LANDING AND SOME HOOKS @ TOP OF WALL. |
|
05/06/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*BOTTOM OF OUTLET STRUCTURE 2/15 OK 2.) COLUMNS G-1 & D-1 OK. |
|
05/05/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*COLUMNS DONE EXCEPT C-1,D-1,A2,B2, 2.) PROGRESS ON VAULT. |
|
05/02/2003 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection 0000* | |
04/28/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1. C3 PAD OK TO TO POUR. 2.) MET WITH P.E. LAURA CARTE ABOUT CLEARANCE FOR TOP BARS TO FORM IN DRAIN CALVERT. PLAN SHOWS 2" INSTALLERS HAVE UP TO 5" CLEARANCE THIS HAS BEEN OK'D BY P.E. |
|
04/25/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) SITE VISIT TO OBSERVE PLACEMENT OF CONCRETE @ COLUMNS. 2.) STEEL BEING SET IN C-3. |
|
04/24/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1. A-1 OK TO POUR. 2.) PLEASE COLUMN NOTES INCORRECT. CORRECT COLS ARE: B-3 & C-3 ALREADY POURED. C-2 AND B-1 COLS ARE OK TO POUR. |
|
04/23/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) D3 PLACEMENT OBSERVED OK 2.) A 2 OK TO POUR. 3.) CLOUMN D4 OK TO POUR. |
|
04/22/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*B1 OK TO POUR. 2.) CD REQUIRED BETWEEN A1 & AZ CORNER BARS REQ. ON #S HORIZ @ A1 SLOPE. |
|
04/18/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) E3 POURED 2.) DISCUSSED WITH BOB LENON OF TUCSON WATER WHAT TO WATCH FOR DURING CONCRETE PLACEMENT. |
|
04/17/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*B4 & D4 PER SPECIAL INSPECTION REPORT OK TO POUR. | |
04/15/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*C4 OK TO POUR: D4 REQUIRES COLUMN BARS TO BE PLACED. | |
04/14/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*POURING C2 & E2 TODAY. | |
04/11/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*D1 COMPLETE E2 COMPLETE. 3.) C2 REQUIRES CONST. #S TO SLOPE. |
|
04/10/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* | |
04/09/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) B2 & E2 OK TO POUR. 2.) D1 STILL NEEDS CTJ DOWELS AND WATER STOP. |
|
04/08/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* 1.) E1 COMPLETE. 2.) D1 & D2 STILL NEED CTJ DOWELS. 3.) B2 NEEDS CONTINOUS #S AT SLOPE LINES, DOWELS @ CTJ AND COLUMN REINFORCEMENT. |
|
04/04/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) F2 COMPLETE 2.) E-1 STILL NEEDS CTD DOWELS LINE C AND CONTINUES #5 @ LINE 1. |
|
04/02/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*F1 OK TO POUR. | |
04/01/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*F3 COMPLETE 2.) F REQUIRES CORNER BARS ON ALL #S HORIZ. UP TO FLAT SECTION. 3.) VALVE VAULT WALL WEST END 1S' OF N & S. |
|
03/28/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1. F3 & E4 2.) OK TO POUR WHEN SPECIAL INSPECTOR OBSERVES FINAL PLACEMENT OF STEEL & EXPANSION JOINT. 3.) FINISH INSTALLING CONTINOUS BARS THROUGH LINE D. 4.) INSTALL LOWER MAT @ DRAIN GROOVE. 5.) 3" CLR TO EARTH REQUIRED FOR LOWER MAT @D-3 COLUMN. 6.) FINISH INSTALLING SYNTHETIC SPONAGE @ EXPANSION JOINT. |
|
03/26/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*F4 OK TO POUR/PUMP BARREL FOUNDATION OK TO POUR. | |
03/25/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*SITE VISIT TO OBSERVE CONCRETE PLACEMENT AND GENERAL INSTALLATION OF REINFORCEMENT. | |
03/24/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*F5 OK TO POUR. 2.) E6 REQUIRES REINFORCEMENT ALONG NORTH EDGE PER PLAN. BARS BEING INSTALLED AT THIS TIME. OK TO POUR AFTER SPECIAL INSPECTOR APPROVES FINAL PLACEMENT. |
|
03/21/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* 1.) D6, E6 OK TO POUR. |
|
03/20/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*D 2 & F6 OK TO POUR. | |
03/17/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*SLAB A-5,B5,E5. | |
03/13/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000* 1.) #5 lap splice bars along line a have not yet been installed due to shipping eerror. 2.) ok to pour only when competion of #1 deserved by myself or special inspector. |
|
03/12/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*PARTIAL OK TO POUR C5 RINGS ON CLOUMN TO BE INSTALLED AFTER POUR. | |
03/11/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 0000*HOLD POUR AREA C-5 UNTIL FURTHER INSP. 1.) PLEASE HAVE ALL COLUMNS STEEL AND CTU AND EJ DOWELS ETC IN PLACE. 2.) LAYOUT OF MAT AND SIZE OF #8 VENTS OK. |
|
03/10/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*AREA B6 OK TO POUR 2.) BOND BREAKER COMPOUND REQUIRED ON SURFACE OF CT.J. |
|
03/07/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) PLEASE NOTE SPECIAL INSPECTION IS IN ADDITION TO INSPECTION BY BUILDING OFFICIAL. I WOULD LIKE TO SEE FIELD REPORTS THAT IDENTIFY WHAT WAS LOOKED AT. IS ALSO NEED TO HAVE SPECIAL INSPECTION APPROVED BY DSD. | |
03/07/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*INSPECTED A.5-B.5/4-5 A.) SHEAR PINS NOT INSTALLED FOR EJ & CTU PER DETAIL PP 24. B.) CENTER BULB WATER STOP REQUIRED TO BE SUPPORTED 12" OC. PER DETAILS ON PP 24. C.) EJ & CTU'S ARE 9" WIDE WITH WATER STOP; INSTALL REINFORCEMENT SO THAT 9" IS LARGEST GAP THAT WOULD ENTAIL INSTALLATION OF BARS WITHIN 5" OF JOINT OR PROVIDE RFI FROM ENGINEER OKING DELETION. D.) TAILS LOWERS MAT BARS REQUIRE 2" CLEAR FROM FORM @ TOPS. |
|
03/06/2003 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection 0999* | |
03/04/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*TOP & SIDE SLOPE Z-A/4-5 IS LACKING CORNER BARS PER NOTE 3 PP. 8. IE. ALL SLIDE SLOPE BEND LINE CORNER BARS SHALL BE LAPPED. ABOUT 1/2 OF THE #5 MAT BARS HAVE NOT HAD CORNER BARS INSTALLED AND NONE OF THE # 5 BARS RUNNING HORIZONTALLY UNDER #9 BARS HAVE CORNER BARS INSTALLED. |
|
02/20/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) BOTTOM OF SUMP PIT IN VALVE VAULT OK. OK TO POUR WHEN FINAL FORM CLEARANCE OBSERVED BY SPECIAL INSPECTOR. 2.) 4' MAT (5 #7 EACH WAY) AT BOTTOM OF STAIR COLUMN IS MISSING. CONTRACTOR PLACING MAT @ THIS TIME TO BE CONFIRMED BY SPECIAL INSPECTOR. 3.) #6 DOWELS AT BOTTOM OF STAIR NOT IN PLACE IF DOWELS ARE TO BE EXPOXIED PLEASE PROVIDE RFI. 4.) BOTTOM OF VALVE VAULT OK TO POUR IF ITEMS 2 & 3 ABOVE TAKEN CARE OF. VERBAL OK FROM ENGINEER OK FOR NOW. |
|
02/12/2003 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection 0000*1.) ATTENDED CONST. MEETING WITH CONTRACTOR & ENGINEER NEED TO CHECK ON HAVING SPECIAL INSPECTOR FOR JOB APPROVED. 2.) REBAR IN SUMP PIT 1/17 IN GENERAL COMPLIANCE CLEARANCE TO EARTH AT BOTTOM OF PIT NEEDS TO BE INCREASED. 3.) RFI TO ELIMINATE #11 @ 6" SLAB TO WALL DOWELS. NECESSARYY FOR CLEARANCE PER ACI. CONTINUOUS FLOOR TO WALLS @ 6" O.C. TO REMAIN. |