Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2003 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 01/13/2003 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*/ 1) PROVIDE APPROVED LETTER SIGNED FROM BLDG OFFICIAL |
| 01/09/2003 |
FRAMING |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) JUST PENDING INFO ON HEATER PLATFORM |
| 01/07/2003 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*/ 1) PROVIDE NAIL PROTECTION CHECK THRU-OUT 2) NO TEST ON DWV 3) PROVIDE 1" CLEARANCE FROM COMBUSTIBLES AT ROOF 4) PROVIDE COMBUSTION RELIEF VENTS PER PLAN 5) PROVIDE PLATFORM FOR HEAT UNIT 6) NAIL SHEAR WALLS AT 9" ON CENTER PER PLAN 7) 3 POINT BRG TRUSSES REQUIRE CLIPS AT WALL |