Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2006 | ENGINEERING - FINAL | Approved | ||
| 03/15/2006 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. 1. SUBMIT A REVISED SITE PLAN TO THE C.O.T ZONING AND ENGINEERING DIVISIONS THAT SHOWS ALL MODIFICATIONS AND AS-BUILT CONDITIONS FOR REVIEW AND APPROVAL. 2. TRASH ENCLOSURE IS CONSTRUCTED IN A LEGALLY RECORDED ACCESS EASEMENT. 3. HANDICAP PARKING AREAS HAVE BEEN MODIFIED. 4. PROVIDE CONCRETE WHEEL STOPS WHERE REQUIRED ON THE WEST PERIMETER OF THE SITE. 5. DELETE SIDEWALK SCUPPERS AND SHOW UNDERGROUND STORM DRAINAGE SYSTEM THAT HAS BEEN CONSTRUCTED ON THE REVISED SITE PLAN. |