Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 11/07/2002 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 11/06/2002 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*/ 1) POST BASES NOT IN AND EXHAUST FAN MASTER BATHROOM |
| 11/05/2002 |
FRAMING |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) NOT READY PER MIKE |
| 11/04/2002 |
FRAMING |
|
Denied |
IVRS - Inspection 0950*/ 1) POST BASES MISSING THROUGHOUT PER S2.1. HAVE ENGINEER OF RECORD PROVIDE DOCUMENTATION IF ONLY TWO POSTS, REQUIRE POST BASES OR ALL POSTS INDICATED ON S2.1 AND FRAMING PLAN SHEET 1 IF ALL REQUIRES PROVIDE ENGINEERING REPAIR DETAIL 2) NAIL PROTECT DRYER VENT AT TOP PLATE 3) PROVIDE ELECTRIC BOND TO GAS LINE 4) NAIL PROTECT PLUMBING WITHIN 1 1/4" OF STUD WALL SURFACE 5) FIRE BLOCKS MISSING THROUGHOUT 6) PLUMBING, ELECTRIC AND MECHANICAL OUTSIDE OF WALL CAVITY 7) LATH MUST BE COMPLETE PRIOR TO INTERMEDIATE INSPECTIONS 8) STOPPED INSPECTION TOO MANY ITEMS |