Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/27/2004 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :*/ 1) SOIL WTR TEST IS OK. 2) OVERHEAD WTR DISTRIBUTION IS OK. 3) GAS PRESSURE TEST IS OK. 4) OK FOR DRYWALL. | |
| 05/25/2004 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999*/ 1) CAN NOT HAVE BUSHINGS IN GAS SYSTEM THAT ARE CONSEALED. 2) MUST INSTALL CLOSET RINGS. 3) MUST PROVIDE SAFTY PLATES FOR ANY WTR LINE THAT IS LESS THAN 1½" FROM DRYWALL. 4) MUST CONNECT CONDENSATE DRAIN TO TAIL PIECE OF LAV OR TUB WASTE AND OVERFLOW. 5) MUST PROVIDE WTR TEST ON WASTE AND VENT SYSTEM. |