Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 06/11/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Approved |
IVRS - Inspection 0000*/ 1) PLUMBING FINAL IS OK 2) HCS CONNECTION IS OK 3) OK FOR TEMP C OF O |
| 06/10/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
1) AIR PRESSURE TEST IS OK FOR M.H. # 1, 2, AND 3 IS OK |
| 06/09/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) 8" SITE SEWER DUCTILE, RUN IS OK FROM M.H. #3 WEST TO C.O. IS OK 2) OK TO BACKFILL TRENCH |
| 06/06/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) NOT READY FOR INSPECTION |
| 06/05/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) 8" SITE FENCE FROM M.H.#2 NORTH TO M.H. #3 2) BASES HAVE BEEN SET FOR M.H. 1 & 2 3) OK FOR BACKFILL |
| 06/03/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) 8" SITE SEWER IS OK FROM M.H. #1 WEST TO 20' EAST OF PRIVATE M.H. #2 IS OK 2) OK TO BACKFILL TRENCH 3) WILL VERIFY AIR PRESSURE TEST AT A LATER TIME 4) WILL REQUIRE A REVISED AND APPROVED PLAN ON SITE SEWER BY FINAL SEWER INSPECTION |