Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/26/2002 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) OK TO BACKFILL TRENCH. 3.) NOTE ALL FITTING HAVE HAD A WATER TEST WITH 10' HEAD. 4.) AIR PRESSURE TEST FOR C.W. INTO PAD IS OK. |
| 08/21/2002 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) YARD WATER LINE FROM METER TO SOUTH WEST CORNER OF BLDG. IS OK 3.) NOTE: THIS INSPECTION IS FOR ROUGH PLBG. AND IS NOTED ON APPROVED PLAN 4.) OK TO BACKFILL TRENCH. 5.) HCS CONNECTION & SITE SEWER IS OK TO BACKFILL. |