Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2003 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection 0000* |
| 02/04/2003 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) BACK WATER VALVE, REVERSE COMBOS, PUT BWV IN CENTER 2) DON'T USE SAN T LAYING FLAT 3) CLEANOUTS TO BE SAME SIZE AS HORIZONTAL DRAIN, CLEANOUTS REQUIRED ON ANY BRANCH MORE THAN 5'-0" FROM MAIN TRUNK LINE 3) 1 1/2" = 42" FOR DISTANCE VENT TO WIER 2" =60", 3" =72" 4) OK TO COVER SEWER UP TO 1ST COMBO |