Permit: T02CM01900

Parcel: 13803031E


Addresses:

850 W VALENCIA RD


Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T02CM01900

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
12/08/2010 PLUMBING - FINAL Approved INSPECTIONS COMPLETED WITH TI PERMIT IN 2006
07/11/2005 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
1) PROVIDE VERIFICATION OF GRADE FROM ENGINEER FOR SEWER
2) HAVE CERTIFICATION FOR RPPBP
3) ICE MACHINE REQUIRES BACKFLOW PROTECTION (007 WATTS OR EQUAL) W/CERTIFICATION
4) INDIRECT WASTE PIPING IN KITCHEN REQUIRES MINIMUM ONE INCH GAP
5) FOYER REQUIRES ACCESSIBLE VALVE AND CABLE RESTRAINT
6) I NEED TO SEE ANSUL VALVE AND IT NEEDS TO BE IDENTIFIED
7) H/C LAVS REQUIRE INSULATION KITS-LISTED H/C FAUCETS
8) ALL FIXTURES TO BE CAULKED
9) IN KITCHEN INDIRECT WASTE PIPING TO BE DIRECTLY TRAPPED WITH CLEANOUTS AT CHANGES OF DIRECTION
11/25/2002 PLUMBING - FINAL Denied IVRS - Inspection 0920*
09/13/2002 PLUMBING - FINAL Partial Approval 1.) ABOVE CEILIING OK 2.) GAS PRESSURE TEST OK 3.) SEWER /HCS INSPECTED PREVIOUSLY BY RMYERS OK 4.) PLUMBING FINAL CONTRACTOR DESIRES TEMP C OF O. FOR KITCHEN AND CAFETERIA THESE AREAS SHOW SUBSTANTIAL COMPLETION MINOR CORRECTIONS TO BE INSPECTED ON FINAL OK FOR TEMP. 5.) UCC LEFT AT METER.
08/05/2002 PLUMBING - FINAL Not ready for Inspection CONTRACTOR IS REQUESTING A TEMP C OF O. 2.) HOWEVER, CONTRACTOR HAS A WAYS TO GO BEFORE COMPLETION. AS I UNDERSTAND IT CONTRACTOR IS TRYING TO GET THE KITCHEN AREA OPERATIONAL BEFORE COMPLETION OF THE REST OF THE PROJECT. AS OF RIGHT NOW, THERE ARE 2 EXISTING BATHROOMS OPERATIONAL, AND HOT WATER TO THE KICHEN IS SUPPLIED BY AN EXISTING WATER HEATER. GAS RELEASE IS CONTINGENT ON APPROVAL OF MECH INSPECTOR, AND FINAL CONNECTIONS IN KITCHEN.