Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 06/11/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection 0000* |
| 05/31/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |