Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/27/2004 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 11/12/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* INFILL COMPLETE |
| 11/06/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* WEST & NORTH 1/2 3RD LIFT |
| 11/05/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* OK 4 SOUTH PIERS |
| 11/04/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* 3RD LIFT SOUTH ELEVATION & 2 SOUTH PIERS 2ND LIFT |
| 10/31/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* 2ND LIFT COMPLETE |
| 10/29/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*/ 4 COLS. 1ST LIFT. EAST HALF 2ND LIFT. |
| 10/28/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*WEST 1/2 1ST LIFT |
| 10/27/2003 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* 1ST LIFT (EAST 1/2) |