Permit: T02CM00637

Parcel: 12620001A


Addresses:

3455 E ZOO CT


Inspection Status: Approved

Inspection History: POOL/SPA PLUMBING

Permit Number - T02CM00637

Inspection Description - POOL/SPA PLUMBING

Inspection Status - Approved

Date Description Inspector Results Comments
11/05/2004 POOL/SPA PLUMBING Approved IVRS - Inspection :*
08/05/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection :*/ 1) PIPING INTO LEISURE POOL MANIFOLD FOR PLAY EFFECTS TOWER TIE 50 PSI WATER TEST OK
04/15/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ ALL POOL PIPING FROM POOLS BOTH PEANUT AND LEISURE INTO POOL EQUIPMENT ROOM 50 PSI WTR TEST OK.
04/12/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 50 PSI WTR TEST ALL PIPING BOTH POOLS - PEANUT AND LIESURE - EXCEPT TWO 2" FILL LINES TO LEISURE POOL AND FROM 6" TEE TO 4" LINES FOR PROPULSION UNIT AT ISLAND OF LEISURE POOL OK.
04/09/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 8" ACTIVITY SUCTION TO WEST SIDE OF LEISURE POOL 50 PSI TEST INTO MECH ROOM. 8" PROPULTION SUCTION TO NORTHSIDE, 50 PSI TEST INTO MECH ROOM. 6" PROPULSION RETURN TO NORTHSIDE 50 PSI TEST INTO MECH ROOM ALL LIESURE POOL.
04/05/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 50 PSI WTR TEST ON ALL PIPING FOR LIESURE POOL TO POOL EQUIPMENT HEADERS IN MECH. ROOM, SOUTH AND EAST PIPING EXCEPT 6" GUTTER AT 8" ACTIVITY SUCTION TO CONTINUE TO EQUIP. ROOM. TWO 8" ACTIVITY SUCTIONS ON WEST END FROM POOL INTO MECH. ROOM. 50 PSI WTR TEST.
03/03/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 2-4" PROPULSION SUPPLYS TO 4-1½" HEADS ON NORTH AND SOUTH ENDS OF PEANUT POOL TO OUTSIDE POOL AREA. 50 PSI TEST APPROVED.
02/25/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 1) 4-6" GUTTER SUCTIONS STUBBED TO EXTERIOR OF LEISURE POOL 2) 4" GEYSOR SUPPLY TO 6 HEADS, 3" PIPE FALLS SUPPLY, 1" PULL REPOS SUPPLY 2 1/2 WATER CURTAIN, 2" BAR AND 2" ARCH SUPPLY 3) WATER TEST 50 PSI APPROVED 4) ALL STUBBED TO EXTERIOR OF LEISURE POOL
02/24/2004 POOL/SPA PLUMBING Not ready for Inspection IVRS - Inspection 0000*
02/19/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 6" WTR CURTAIN SUPPLY FOR PEANUT POOL FROM STUB UP IN ISLAND TO POOL EXTERIOR AND 2" WALL SPRAY FOR SAME. 50 PSI TEST APPROVED.
02/17/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 50 PSI WTR TEST 8" CURRENT CHANNEL PROPULSION SUCTION #1 OK. 50 PSI WTR TEST 4" SOUTH PROPULSION SUPPLY OK. BOTH STUBBED OUT OF POOLS.
02/13/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 6" INLET SUPPLY RETURNS FROM SOUTH POOL EXTERIOR TO ALL 1½ FLOOR RETURNS ON SYSTEM IN SHALLOW END [EAST] OF POOL. 50 PSI WTR TEST OK.
01/26/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 50 PSI TEST ON 6" FLOOR RETURN WITH [13] 1½" FLOOR RETURNS IN DEEP END OF LIESURE POOL. STUB OUT OF POOL FORM.
01/23/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ LEISURE POOL. 2-8" MAIN DRAIN STUBBED OUT OF POOL 50 PSI TEST, APP. 2-8" ACTIVITY SUCTIONS FOR TOYS, 1-8" CURRENT SUCTION 50 PSI APPROVED. STUBBED OUT OF POOL.
01/20/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ LEISURE POOL - 10" HEADER, 2-8" MAIN DRAINS, 2-6" INLET RETURNS, 4-6" GUTTER SUCTIONS, 2-2" FILLINGS, MECH ROOM STUBBED OUT 5'. PEANUT POOL - 1-6" PROPULSION SUPPLY, 1-6" PROPULSION RETURN, 1-2" WALL SPRAY
01/14/2004 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 1) THEARPY POOL 2-3" JET LINES AND AIR LINES, 3" FLOOR RETURNS FOR STEM, 2-2" WATER FILL LINES (NEED TO ONLY SEE COMPLETION OF 2-2 1/2" AIR LINES. 50 PSI TEST PARTIAL 2) LEISURE POOL-SOUTH 8" AND 6" HEADER ON SOUTH WALL STUBBED OUTSIDE BLDG 50 PSI TEST APP. PARTIAL 3) 2" FLOOR SINK IN MECHANICAL ROOM 102 WATER TEST APPROVED 03005 APPROVED
12/12/2003 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ TWO 3" JET RETURNS 50 PSI TEST. TW0 - 2" H20 FILLINGS 50 PSI TEST. 6" INLET RETURN 50 PSI TEST. FLOOR COMPLETE EXCEPT FROM BENCH SOUTH.
12/11/2003 POOL/SPA PLUMBING Partial Approval IVRS - Inspection 0000*/ 8" MAIN DRAIN 50 PSI TEST OK FOR THERAPY POOL. 2-6" GUTTER SUCTION 50 PSI TEST OK FOR THERAPY POOL. 6" JET SUCTION 50 PSI TEST OK FOR THERAPY POOL.