Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/10/2003 | FRAMING | Approved | IVRS - Inspection 0000* | |
| 08/26/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 08/13/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* #201,204,203,205,206,207,208,209,210,211,212,213, 214,216,217,121,122 | |
| 07/28/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* CORRIDOR 112 BEDRM 113 THRU 120. OK TO COVER SOFFITS UTILITY SHAFT 107 OK TO CLOSE. | |
| 07/24/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) 2ND FLOOR WALKWAY CEILING EAST SIDE OF COURT YARD | |
| 07/23/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) 2ND FLOOR BALCONY CEILING-OK | |
| 07/21/2003 | FRAMING | Not ready for Inspection | ||
| 07/18/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) COMPLETE TOP FLOOR OK TO ROCK | |
| 07/15/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) OK TO COVER ALL WOOD FLOORS ON 1ST FLOOR WITH GYP-CRETE | |
| 07/10/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* CEILING 109,110 & 128. PLYWOOD WALKWAY E. SIDE COURTYARD | |
| 07/08/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* EX-GRID 3-4, GRID E-I.8 | |
| 07/07/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*CORR. 121,122 | |
| 07/02/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* # 113, 117, HALL. 112 OK TO HANG & TAPE. # 114, 118, 121, 122, 115, 119, 166, 120 - PARTIAL. | |
| 06/26/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) #101, 102, 103, B05 CEILING, OK TO HANG ROCK | |
| 06/24/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) #107, 108, 129, 109, 110 AND 128 | |
| 06/19/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 06/18/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) BARBQUE GRAD SUITE SOFFIT ROOM #B03 NORT | |
| 06/17/2003 | FRAMING | Not ready for Inspection | IVRS - Inspection 0000* | |
| 06/16/2003 | FRAMING | Partial Approval | STAIRWAY #3 PLYWOOD 2) GRID I-K TO GRID 7 3) #B-10 | |
| 06/11/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) ROOM 106 AND 202 | |
| 06/09/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) DRYWALL CILING AT ROOMS #113 AND 114 2) R.C. CHANNEL CEILING AT ROOM #215 AND 127 3) FRAMING AT #B05, B06, B13, B08, B09, B12 AND B10 WALLS | |
| 06/06/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) DRYWALL AT CEILING #112 (CORRIDOR) AND ROOM #115-116, #117-WEST WALL OF #108-ALL WALLS AND CEILING AT ROOM #B-01 2) R.C. CHANNEL AT ROOM #216 AND #217 | |
| 06/04/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) OK CEILING DRYWALL ROOM NUMBERS 216-217 2) OK R.C. CHANNEL AT ROOMS 211, 212, 214 AND 213 | |
| 06/03/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) OK R.C. CHANNEL AT ROOMS #208-209 AND #210 | |
| 06/02/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) ROOM HALL 112 | |
| 05/30/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*/ 1) RC CHANNEL ROOM #115, 116, 117, 118, 119, 120, 113, 114, 121 AND 122 FOR WALL FRAMING ROOM 104 AND 105 | |
| 05/23/2003 | FRAMING | Not ready for Inspection | IVRS - Inspection 0000* | |
| 05/20/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*ST WALL ANCHOR GRID 2 BET. E TO I. | |
| 05/16/2003 | FRAMING | Partial Approval | 1) CEILING SHEETROCK AT LIBRARY AND MAIN ENTRANCE 2) PURLIN ANCHORS AT TOP OF TRUSSES AT ROOM 110-109 3) OK ABOVE CEILING AT ROOM 124-125 | |
| 05/13/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*STAIRWAY #1. | |
| 05/12/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*GRIDLINE E-I 3.34 ROOM 301,302. PENDING OTHER TRADES APPROVAL. |
|
| 05/09/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*STAIRWAY #1 THRU 1ST FLR. LID. | |
| 05/07/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*@ LIBRARY CEILING ONLY. | |
| 05/06/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*OK FRAMING R.C. CHANNEL @ STAIRWAY #1. | |
| 05/02/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*ROOM 202,201, CORRIDOR 203 GRIDLINE 10-5 AND 204 PANEL. | |
| 05/01/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*gridline C to H. Gridline 2-3 gridline I.8 crossover. colume k.5 2.6. trash enclouser stem wall & chiller yard. |
|
| 04/30/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*OK R.C. CHANNEL @ RM'S B09 - B05 B08 108. GRIDLINE 5 T0 10 GRIDLINE B T0 E. | |
| 04/24/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*ROOF FRAMING FROM BASEMENT 1ST FL, 2ND FL. FROM G.L. 5 TO 10 FROM G.L. B TO G. | |
| 04/18/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*GRID F 123 THRU 126 BETWEEN 5 & 4. | |
| 04/17/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 04/11/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*SENIOR ROOM #210,#216,#217. | |
| 04/10/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* PERFIN. ANCHORS GRIDLINE 2.5. -10. | |
| 04/08/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*OK R.C. CHANNEL @ RMS 106-104-105. | |
| 04/03/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*OK PRE-SLAB @ MECH RM. @ RMS 103-101-114-115-104. 2.) STEM & HANDICAP RAMP & PORCH GRIDLINE F FROM 2.5'4" TO TOP OUT. 3.) OK ATTACHMENT OF R.C. CHANNEL GRIDLINE 4 TO 8 RMS B-124 B-125. |
|
| 03/28/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*lower level basement area. | |
| 03/21/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*105. | |
| 03/19/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 03/18/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 03/17/2003 | FRAMING | Partial Approval | RM 104,106 PURLIN ANCHORS. OK. | |
| 01/21/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*1ST FLOOR DECK FRAMING. | |
| 01/17/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000* | |
| 01/14/2003 | FRAMING | Partial Approval | IVRS - Inspection 0000*OK INSTALL FLOOR SHEATHIN @ B101-B103 B114. ALL NAILED. |