Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T02BU00961


Addresses:

10440 E VALENCIA RD


Inspection Status: Partial Approval

Inspection History: GRADING - FINAL

Permit Number - T02BU00961

Inspection Description - GRADING - FINAL

Inspection Status - Partial Approval

Date Description Inspector Results Comments
11/30/2005 GRADING - FINAL Partial Approval received a Engineers letter of substantial conformance from Rick Engineering for the roads, basins and drainage ways.
11/30/2005 GRADING - FINAL Approved ALL PUNCHLIST ITEMS FROM PREVIOUS INSPECTION 8/23/05 HAVE BEEN MET/RESOLVED.
11/21/2005 GRADING - FINAL Partial Approval MET WITH GEORGE (LENNAR HOMES) 481-2725

SILT FENCE ON MEADOW WILLOW (WEST END) SOUTH SIDE OF DRAINAGE STRUCTURE NEEDS TO BE REMOVED.
RE-HYDRO SEED BASIN 2
BASIN #6 NEEDS TO HAVE THE SW SIDE GRADED TO DRAIN.

GEORGE WILL CALL FOR RE-INSPECT
10/26/2005 GRADING - FINAL Correction Required VISITED SITE WITH JIM TODAY. SOME WORK HAS BEEN DONE ON THE BASINS. ADDITIONAL WORK TO BE DONE BEFORE FINAL RELEASES
08/23/2005 GRADING - FINAL Correction Required The following items need to be completed or addressed prior to final acceptance of the grading permit.
1.An Arizona Registered Professional Civil Engineer must certify that the drainageways and detention/retention basins have been constructed in accordance with the approved plans.
2.Common Area B-2, water stands at the outfall from the 24 inch pipe, grade to drain.
3.Basin #2, the inlet on Pacific Willow Dr. has standing water, grade to drain.
4.Basin #3, Ponding water at the outlet to the 30 inch pipe regrade to drain.
Construct the outfall protection per detail "D" on sheet 9
5. Basin #6, ponding water at both the inlet and outlet to the basin, grade to drain.
6. Basin #4 backfill the ends of pipe at the outfall to Atterbury Wash.
7.Repair the erosion to the slope along the edge of Common Area A-26
8. All grass and weeds need to be trimmed within the basins to a height of 6 inches.
9. Repair the damaged sidewalk on Pacific Willow Dr.
08/19/2005 GRADING - FINAL Correction Required Started final grading inspection at the site today, will continue next week.
04/20/2005 GRADING - FINAL Partial Approval MET WIT HOA PRESIDENT TO DISCUSS NEEDED CORRECTIONS FOR RETENTION/DETENTION BASINS WITHIN DESERT WILLOW. ALSO ERROSION PROBLEMS ARE OCCURING WITHIN THE EASTERN PORTION OF THE SITE AT THE AUTERBURY WASH. THESE CONCERNS HAVE BEEN VALIDATED AND WILL BE HANDLED WITH US HOMES ACCORDINGLY.
03/22/2005 GRADING - FINAL Correction Required Met with Gorge C. with Lenarr Homes to discuss wich detention retention basins need to be modified to inhibit ponding of water over the 24-hour time limit. George explained he would keep informed of the plan to solve the problem.