Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 06/06/2002 |
PLUMBING - PROGRESS |
|
Approved |
IVRS - Inspection 0000* WATER TEST ON SEWER SECTION OK. |
| 06/05/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 04/17/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000*1.) 6" SITE SEWER FROM LOT #22 SOUTH TO LOT #37 IS OK. 2.) OK TO BACKFILL TRENCH 3.) WILL VERIFY WATER TEST @ LATER TIME. |
| 04/15/2002 |
PLUMBING - PROGRESS |
|
Denied |
IVRS - Inspection 0999*1.) 6" SEWER MAIN BETWEEN M.H. #5 AND CO #12. HAS SERIOUS BACK PITCH AND TWEEKED COUPLINGS. 2.) ALL MANHOLES REQUIRE A FLEXIBLE COMPRESSION JOINT @ INLET & OUTLETS OF SEWER SEE SECTION 719.6 94. |
| 03/25/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/15/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/13/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/12/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000*WATER TEST OK INSTALLED. |
| 03/11/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/08/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/07/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/06/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 03/01/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/28/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/25/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/22/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000*SEWRE OK TO COVER AS MARKED ON PLAN CO #3 TO M.H. #3. |
| 02/21/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000*AS NOTED ON PLAN . |
| 02/20/2002 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000* |
| 02/15/2002 |
PLUMBING - PROGRESS |
|
Denied |
IVRS - Inspection 0000*SEWER MUST BE EXPOSED & TESTED. |