Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2003 | PLUMBING - SEWER HCS CONNECT | Approved | ||
| 04/09/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000* | |
| 03/28/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000*AIR PRESSURE TEST FOR SITE SEWER FROM M.H. #3 EAST TO END OF RUN ONLY. | |
| 03/21/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000* 1.) SITE SEWER FROM C.O. 5-5 EAST TO C.O. 5-6 IS OK 2.) OK TO BACKFILL TRENCH. |
|
| 03/19/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | SITE SEWER FROM M.H. #2 EAST TO CO. 5-5 IS OK TO BACKFILL TRENCH. | |
| 03/18/2003 | PLUMBING - SEWER HCS CONNECT | Denied | IVRS - Inspection 0999*NO APPROVED DRAWINGS ON SITE. | |
| 03/07/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000*FROM M-H #2 40' 6" SDR 35 NO TEST CONTRACTOR WILL TEST AT LATER DATE PLEASE PROVIDE VARIFICATION OF GRADE. | |
| 03/04/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | 1.) AIR PRESSURE TEST FOR SITE SEWER FROM M.H. #1 NORTH TO M.H. #2 AND NORTH FROM M.H #2 TO M.H #3 IS OK. 2.) MANDREL WAS PULLED FROM M.H. #1 TO #2 & #3. 2.) MANDREL WAS PULLED FROM M.H. #1 TO #2 & #3. |
|
| 03/03/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000*1.) VACCUM TEST FOR M.H. 1,2,3, IS OK 2.) MANDREL WAS PULLED FROM M.H. 1 TO #2 MANDREL SNAGED UP @ MECH COUPLING. |
|
| 02/12/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000*1.) BASES HAVE BEEN SET FOR M.H. #1,2 & 3. 2.) OK TO STACK MAN HOLES. |
|
| 02/11/2003 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection 0000*NOT READY FOR INSPECTION. | |
| 02/03/2003 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection 0000* 1.) 8" SITE SEWER FROM M.H. #1 NORTH TO M.H. #2 IS OK TO BACKFILL. 2.) OK TO BACKFILL @ ENTRANCE OF TRAILER PARK. 3.) WILL REQUIRE VERIFICATION OF GRADE ON ENTIRE SITE SEWER SYSTEM LESS HCS BRANCHES EVERY 50' INTERVALS PRIOR TO BACKFILL. 4.) WILL AIR TEST SYSTEM @ A LATER TIME. |