Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 03/14/2001 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection 0000*OK TO BACKFILL |
| 02/26/2001 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0999* 1) SEE SEC. 708.0 94 UPC GRADE OF HORIZONTAL DRAINAGE PIPING 2) SEE SEC 718.0 GRADE SUPPORT AND PROTECTION OF BLDG SEWERS 718.1 UNIFORM SLOPE NOT LESS THAN 1/4" PER FOOT 718.2 SEWER LAID ON A FIRM BED THROUGH OUT ITS ENTIRE LENGTH 718.3 SHALL NOT BE INSTALLED LESS THAN ONE FOOT BELOW THE SURFACE OF THE GROUND 723.0 WATER TEST FROM LOWEST TO HIGHEST POINT |
| 02/20/2001 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0999* 1) NO WATER TEST ON LINE 2) UNAPPROVED MATERIALS USED AT TIE IN 3) A SANTEC ON ITS BACK IS NOT APPROVED CLEAN OUT FITTING 4) HORIZONTAL TO HORIZONTAL CHANGE OF DIRECTION MUST BE A SWEEP 5) VERTICAL TO HORIZONTAL CHANGE OF DIRECTION MUST BE THROUGH A WYE BRANCH FITTING OR EQUIVELENT SWEEP 6) ABS MUST BE KEPT AT LEAST 12" BELOW GRADE LESS THAN 12" TO BE CAST IRON 7) HAVE TENANTS SIGNED A JOINT SEWER USER AGREEMENT? |