Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 01/25/2002 |
PLUMBING - FINAL |
|
Approved |
1.) ALL CORRECTIONS MADE OK 2.) PRESSURE TEST OK 3.) PIPING OK 4.) VALVES AND FLEXES OK 5.) OK FOR GAS 6.) UCC LEFT AT METER 7.) THIS ALSO APPROVED T01PL02555. |
| 01/18/2002 |
PLUMBING - FINAL |
|
Denied |
IVRS - Inspection 0999*1.) GAS PIPING STILL NOT INSTALLED PER PLAN 2.) GAS PIPING INDICATED ON APPROVED PLAN TO BE RUN FULL SIZE ALL THE WAY TO THE UNIT.3.) BE SURE AND CHECK ALL INSTALLED PIPING AGAINST WHAT IS INDICATED ON APPROVED PLAN 4.) AGAIN, PER TABLE 12-10 CONNECTORS TO BE 3/4" NOMINAL |
| 01/14/2002 |
PLUMBING - FINAL |
|
Cancelled |
IVRS - Ri canceled |
| 01/09/2002 |
PLUMBING - FINAL |
|
Denied |
IVRS - Inspection 0999*1.) GAS PIPING IS NOT INSTALLED PER PLAN 2.) REVIEW TABLE 12-10 CAPACITIES OF LISTED METAL APPLIANCE CONNECTORS. 175,000 BTU APPLIANCE WOULD REQUIRE 3/4" NOMINAL FLEX. 3.) I HAVE REVIEW LETTER FROM WINNELSON CO CONCERNING THE LISTING OF INSTALLED PIPING IT WILL GO ON FILE DOWNTOWN BE ADVISED I'M NOT CONVINCED THAT THE PIPING INSTALLED IS THE APPROVED PIPING YOU PURCHASED. FROM NOW ON, IF THERE IS NO LISTING ON THE PIPE, IT WILL BE REJECTED. |