Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2003 | PLUMBING - ROUGH, SOIL | Approved | SOIL WTR TEST IS OK - ROOM 21, 25 | |
| 02/03/2003 | PLUMBING - ROUGH, SOIL | Partial Approval | 1.) ALL RISERS HAVE BEEN WRAPPED 2.) OK FOR CONCRETE. |
|
| 01/29/2003 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection 0000*UNDER SLAB COMPLETE. | |
| 01/27/2003 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection 0000*1.) REPAIR MADE TO UPPER BRANCH, NEW SECTION INSTALLED. 2.) NORTH BRANCH FOR TENANT SPACE DRAIN PIPING OK. (BACK TO BACK BATH, FLOOR SINK, WATER FOUNTAIN. |
|
| 01/23/2003 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) OK TO BACKFILL TRENCH UP TO WEST UPPER 4" BRANCH LINE DUE TO CRACK IN PIPE. 3.) RE TEST SYSTEM. |