Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2003 | ENGINEERING - FINAL | Approved | ||
| 07/07/2003 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED, FINAL NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #9190 FOR PERMIT # T01BU02371 IS COMPLETED AND ACCEPTED. THE FOLLOWING ITEMS NEED TO BE ADDRESSED ON THIS SITE: 1) COMPLETE ALL DRAINAGE WAYS ADJACENT TO THIS SITE. 2) COMPLETE ALL ROOF GUTTER INSTALLATIONS AS PREVIOUSLY DISCUSSED. | |
| 06/19/2003 | ENGINEERING - FINAL | Partial Approval | 1) ROOF DRAINAGE FALLS DIRECTLY ONTO ADJACENT SIDEWALKS IN SOME AREAS, THIS WATER NEEDS TO BE REDIRECTED. 2) COMPLETE ALL WORK ADJACENT TO THE SIDEWALKS. ALL WORK REMAINING NEXT TO THE SIDEWALK/PEDESTRIAN ACCESS AREAS WILL NEED TO BE BARRICADED. 3) THE FINAL C OF O WILL NOT BE GIVEN TO THIS SITE UNTIL THE FINAL GRADING INSPECTION #9190 FOR PERMIT #T01BU02371 IS COMPLETED AND ACCEPTED |