Inspection History Details
Inspection Status: Not ready for Inspection
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2007 | FRAMING | Not ready for Inspection | IVRS - Inspection :* | |
| 04/04/2007 | FRAMING | Not ready for Inspection | IVRS - Inspection :* REFEE WILL APPLY |
|
| 10/06/2006 | FRAMING | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) ALL INTERMEDIATES MUST BE COMPLETE, IE: ELECTRICAL, PLUMBING AND MECHANICAL PRIOR TO APPROVAL OF FINAL FRAME AS PREVIOUSLY REQUESTED 2) REFEE WILL APPLY |
|
| 04/10/2006 | FRAMING | Not ready for Inspection | IVRS - Inspection :* 1) NEED TO COMPLETE ALL INTERMEDIATES BEFORE FRAME INSPECTION 2) NEED ONE SET OF APPROVED PLANS ON SITE |
|
| 11/22/2005 | FRAMING | Denied | IVRS - Inspection : See detailed listing on site.| 999*REVISE PLANS TO SHOW STEEL FRAMING REAR PATIO CALLS OUT TJI'S FRAMED W/4X 8 ?? REVISE T-STRAPS MISSING AT PATIO COLUMNS. LEDGERS CALL OUT 3/4" BOLTS |