Inspection Status: Approved
Inspection History: ELECTRIC - TEMP POWER FOR TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 03/26/2002 |
ELECTRIC - TEMP POWER FOR TEST |
|
Approved |
IVRS - Inspection 0000*SIGN OFF SHEET SUBMITTED BOND POSTED |
| 03/25/2002 |
ELECTRIC - TEMP POWER FOR TEST |
|
Denied |
IVRS - Inspection 0245*NOTES 1.) STEEL CONDUIT FOR WATER BOND WIRE MUST HAVE BOND BUSHING AT ONE END OF CONDUIT TO BOND CONDUIT TO WATER BOND. 250-92 NEC. AND 3/4" FOR UFER. 2.) BOND BUSHING REQUIRED ON 4" CONDUIT ENTERING CT CAN AND IN GUTTER 2 1/2" NIPPLE, 3/4" CONNECTORS. PER 250-94 NEC. 3.) HI LEG FOR 3 0 DELTA SYSTEM TO BE ON B 0 BEYOND METERING PER #9287 CITY OF TUCSON ORDIN. CHANGE BLUE TO RED. 4.) INSTALL 2 GROUND ROD 6' MIN APART PER 250 NEC. |