Inspection Status: Approved
Inspection History: ELECTRIC - TEMP POWER FOR TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 11/27/2001 |
ELECTRIC - TEMP POWER FOR TEST |
|
Approved |
IVRS - Inspection 0000* |
| 11/21/2001 |
ELECTRIC - TEMP POWER FOR TEST |
|
Denied |
IVRS - Inspection 0999*LEAVE BUSINESS CARD WITH STATE LIC # AND COPY OF CITY OF TUCOSN BUSINESS LICENSE & PRIVELIDGE TAX CERT.1.) THE RIDGID NIPPLES MUST BE BONDED ON BOTH ENDS (NEC 250). ALL OF THEM 2.) LOCKNUTS MUST BE MADE WRENCH TIGHT AT MAIN SWITCHES AND SUB PANELS. THE LOCKNUTS ARE INSTALLED WRONG SIDE UP, AT PANELS 3.) EACH SUB PANEL REQUIRES THE #6 GRD. WIRE PER PLAN. ISOLATE GROUND & NEUTRAL 4.) REIDRAW THE POWER PLAN TO REFLECT THE CHANGES MADE. 5.) TEP REQUIRES SEALABLE FITTINGS ON RACEWAYS HOUSING FEEDERS TO METER CANS. THE LB MUST BE SEALABLE. |