Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 10/03/2001 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
IVRS - Inspection 0000*/ 1) PER REVISION ON PAGE S-1 |
| 09/21/2001 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) OK TO POUR FOOTINGS |
| 09/05/2001 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) HOW DOES YOUR FLOOR ATTACH TO THE FOOTING? 2) YOU ARE GOING TO NEED A HORIZONTAL BAR AT STEM/FLOOR 3) NEED TO ESTABLISH A TOP OF FTG GRADE, SO YOU NEED A DETAIL PLAN 4) I NEED TO KNOW WHAT YOUR BLDG |
| 08/23/2001 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Denied |
IVRS - Inspection 0800*/ 1) ON YELLOW SHEET RISER DIAGRAM, PLUMBING AS SHOWN 2) FROM LAST INSPECTION USE LONG SWEEP 90 DEGREES AT HORIZONTAL CHANGE OF DIRECTION AND WHEN BORING VERTICAL TO HORIZONTAL 3) INSTALL 2 WAY CLEANOUT AT EXTERIOR OF NEW ADDITION 4) ALL FTGS TO BE 12" BELOW NATURAL GRADE |