Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 08/31/2001 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 08/06/2001 |
FRAMING |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) NEED 1" CLEARANCE AT FLUE PIPE 2) NEED GROUND RODS INSTALLED FOR CABLE DROP 3) COMPLETE FINAL TIE IN ON MECHANICAL |
| 07/31/2001 |
FRAMING |
|
Denied |
1) WATER HEATER FLUE NEEDS 1" CLEARANCE FROM COMBUSTIBLES MATERIALS 4) UFER BROKE 5) REVISE SITE PLAN ADD STORAGE SHED AND CARPORT |
| 07/20/2001 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*1.) REVISE PLANS TO SHOW AS BUILT. FRAMING OR BUILD ALL BEARING AND PARTITION WALLS PER PLAN. 2.) PLUMBING MUST BE INSIDE FRAMED WALL. 3.) PLUMBING & ELECTRIC IN OFFICE ALONG TOP OF BEARING WALL MUST BE MOVED TO PROTECTED LOCATION. 4.) N.W. CORNER AT OFFICE HAS 2 RAFTERS THAT ARE NOT PLACED ON A STRUCTURAL HEADER. |