Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 07/15/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
MASONARY PRE GROUT OK. |
| 07/12/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Denied |
IVRS - Inspection 0999* 1.) NO PAPER MESH, OR FILL MATERIAL IN PLACE TO ALLOW POURING OF BOND BEAM. 2.) KEEP VERTICALS CENTERED IN GROUT CELL. 3/4" MINIMUM DISTANCE FROM INSIDE FACE REQUIRED. 3.) DO NOT PLACE FRONT WINDOW FRAMES BEFORE BOND BEAM IS IN PLACE. |
| 07/09/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000* |
| 06/27/2002 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection 0000*1ST LIFT. |