Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 07/25/2001 |
PLUMBING - INTERMEDIATE |
|
Approved |
IVRS - Inspection 0000*1) SOIL WATER TEST FOR UNIT 3-B2 IS OK 2.) OVERHEAD WATER DISTRIBUTION IS OK 3.) OK TO DRYWALL UPON BLDG. INSPECTOR APPROVAL. |
| 07/24/2001 |
PLUMBING - INTERMEDIATE |
|
Denied |
IVRS - Inspection 0999* |
| 07/23/2001 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection 0000*1.) SOIL WATER TEST FOR UNITS 3-B NORTH AND CENTER UNITS ARE OK 2.) OVERHEAD WATER DISTRIBUTION FOR 3-B UNIT 2,&3 3.) UNIT 3-B-1 SOIL WATER TEST WAS DOWN. |
| 07/19/2001 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
IVRS - Inspection 0000*1.) NOT READY FOR INSPECTION. |
| 07/18/2001 |
PLUMBING - INTERMEDIATE |
|
Denied |
IVRS - Inspection 0999*1.) SOUTH UNIT REQUIRES A WATER TEST ON SOIL ALL THE WAY TO THE TOP OF VENTS. 2.) CENTER UNIT 3" WASTE FOR 2ND FLOOR EXCEEDS 135 RULE. 3.) NORTH UNIT WATER TEST WAS DOWN. |
| 07/17/2001 |
PLUMBING - INTERMEDIATE |
|
Denied |
IVRS - Inspection 0999*1.) NOT SURE WHICH LOT IS 3-B |
| 07/12/2001 |
PLUMBING - INTERMEDIATE |
|
Denied |
IVRS - Inspection 0999*1.) ABS SHIMS NOT APPROVED BRACING 2.) PLUMBERS TAPE NOT APPROVED STAP 3.) SUPPORT ABS VERTICALLY WHERE NEEDED 4.) SUPPORT PEX PIPING WHERE LOOSE IN THE WALL HORIZONTAL TO HORIZONTAL CHANGE OF DIRECTION TO BE WYE BRANCH OR EQUIVALENT SWEEP. |