Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/22/2002 | PLUMBING - FINAL | Approved | LOCATED MISSING PAINT BOOTH ON THE PLAN. PLUMBING INSTALLED PER PLAN. 2.) PLUMBING FINAL OK RPPBP CERTIFICATION ON FILE W/TUCSON WATER 3.) OK FOR C OF O PENDING ANY OTHER INSPECTIONS |
|
09/20/2002 | PLUMBING - FINAL | Denied | IVRS - Inspection 0999*1.) NO REVISED GAS PLAN ON SITE NEED TO SEE REVISED APPROVED PLAN 2.) PAINT BOOTH ON EAST SIDE OF BLDG HAS GAS PIPED UNDER SLAB. CHECK REVISED APPROVED PLAN FOR CORRECT INSTALLATION. I BELIEVE UNDER SLAB GAS NEEDS TO BE SLEEVED AND VENTED CHECK PLAN. | |
05/08/2002 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000*SEC SHEET #2 GAS LINE NOT INSTALLED AS PER APPROVED PLAN PLEASE PROVIDE APPROVED REVISED PLAN OR INSTALL AS PER APPROVED PLAN. | |
04/19/2002 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection 0000*1.) CLEAN OUT ON SINK ACORN SUBMITTED A REVISED DRAWING INSTALLED PER APPROVED PLAN 2.) WATER CLOSET CLEARANCES OK 3. THIS COMPLETES ALL WORK INSIDE. 4.) STILL UNDER CONSTRUCTION PAINT BOOTH ON EAST SIDE OF BLDG. 5.) PLAN DOES NOT SHOW GAS PIPING TO PAINT BOOTH HOWEVER BOOTH REQUIRES GAS GAS PIPING AND PRESSURE TEST OK OK TO COVER. REVISE PLAN SHOWING ADDITIONAL GAS, WILL CHECK REVISION ON FINAL. | |
12/19/2001 | PLUMBING - FINAL | Denied | IVRS - Inspection 0999*1.) THERE ARE TWO OUTSTANDING ISSUES ON THIS JOBSITE THAT NEED TO BE RESOLVED C.D. ON SINKS & CLEARANCES ON WATER CLOSETS THESE NEED TO GO THRU ARCHETECT, IN THE MEANTIME, THERE IS NO REASON A TEMP C OF O. CANNOT BE ISSUED. 2.) OK FOR TEMP C OF O. PENDING ANY OTHER INSPECTIONS. | |
12/12/2001 | PLUMBING - FINAL | Denied | IVRS - Inspection 0999*1.) WATER CLOSETS REQUIRE 15" FROM SIDEWALL OR OBSTRUCTION TO CENTER 2.) READ PLUMBING KEYNOTE #7 ALL SINKS REQUIRE CLEAN-OUTS ALSO REFLECTED ON ISOMETRIC 3.) CONTRACTOR TO INSURE ALL WATER CLOSETS ARE CAULKED. | |
12/07/2001 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000*1.) NOT READY FOR INSPECTION. | |
12/04/2001 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000*1.) NOT READY FOR INSPECTION. 2.) HAVE THE PLUMBER WALK THRU AND COMPLETE HIS PUNCH LIST BEFORE CALLING IN FINAL INSPECTION HINT CHECK CLEAN OUTS ELEVATION AND CLEARANCES ANCHORS AND SUPPORTS. | |
10/15/2001 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection 0000*1.) NOT READY FOR INSPECTION. |