Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
Permit Number - T01CM00202
Inspection Description - PLUMBING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2005 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 05/27/2005 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 09/29/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/4 - 4" EXISTING RAIN DRAINS BETWEEN COLUMN LINES 102 &109 TIEING INTO 8" MAIN RAIN DRAIN WATER TEST FOR WEST TICKETING AREA OK. 6 - SETS OF RAIN DRAINS & OVERFLOW RAIN DRAINS FOR ROOF AT LINK AREA WATER TEST COLUMN LINES 33 TO 41.1 + PER PLAN OK. 2-4" 2-3" 1-4" 1-4+3" | |
| 09/23/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/AT COLUMN LINE Z & A1 FROM COLUMN LINE 102 TO 109 RAIN DRAINS AND OVERFLOW RAIN DRAINS WATER TEST OK EXCEPT FOR EXISTING RAIN DRAINS TO BE TIED INTO RAIN DRAIN PIPING AND TESTED AT LATER DATE. | |
| 09/08/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/1)RAIN DRAIN & OVERFLOW RAIN DRAINS AT COLUMN 1 & 102 AND Y & Z WATER TEST OK 2)RAIN DRAIN & OVERFLOW RAIN DRAIN AT COLUMN 33 & 33.2 AND X5 & Z WATER TEST OK |
|
| 08/20/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :AIR PRESSURE TEST ON WEST CONCOURSE 6" FORCED SEWER MAIN ACROSS ROOF FROM SEWER EJECTOR PUMP ROOM TO 6" STUB UP FROM UNDERGROUND WITH CLEANOUT AT W9+WX OK | |
| 08/03/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/ 1) 8" RAIN DRAIN UP FROM BAGGAGE AT COLUMN LINE 30 + A TO TICKETING 4" RAIN DRAINS FOR COLUMN LINE 26-30 AT COLUMN LINE 21 + 22 WATER TEST OK | |
| 08/02/2004 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 07/29/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/ 1) WATER TEST ON RAIN DRAIN OVERFLOW PIPING BETWEEN COLUMN LINE 26-30 AT COLUMN LINE A 2ND LEVEL EAST TICKETING OK 2) WATER TEST ON TRENCH DRAIN FOR WEST BAGGAGE COLUMN LINE 104-109 AT COLUMN LINE Y OK. INCLUDING 3" STUB UPS FOR CANOPY DRAINS AT 6 LOCATION TRANSITION TO STAINLESS OK | |
| 06/24/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/ 6" OVERFLOW RAIN DRAIN AT CENTERLINE 23 AND Y BACK TIES INTO 6" FROM WEST AND ROOF SECTION BETWEEN CENTERLINE 23 AND CENTERLINE 24. WTR TEST OK. 4" RAIN DRAIN REDUCES TO 3" AND CATCHES SAME AREA WTR TEST OK. 4" SEWAGE EJECTOR PIPING FROM 8" FROM SEWAGE EJECTOR SUMP UP TO 6" GRAVITY DRAIN ACROSS ROOF AND DOWN TO C.O. IN ROADWAY ABOUT 10' FROM MANHOLE AT COLUMN LINE 18 AND F. 7 PSI AIR TEST INSTALLED PER APPROVED PLAN OK. | |
| 04/29/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :*/ 4" UP TO 4" AREA DRAIN AND CONTINUE TO 3" UP FOR ROOF DRAIN AT LEVEL 2 CENTERLINE Y1 AND 26, 27, 28, 29 OK WTR TEST PENDING SEEING APPROVED PLAN WITH SIZING. 3" UP TO 3" AREA DRAIN CONTINUES TO 3" UP FOR ROOF DRAIN AT LEVEL 2 WTR TES OK PENDING SEEING APPROVED PLAN WITH THIS SIZING PAGE 3P2.14 AT CENTERLINE Y1 AND 30. 2" FLOOR SINK DRAIN TO SUMP PUMP BASIN AND 2" VENT TO 8' ABOVE FINISHED FLOOR IN AHV #104. WILL REQUIRE WTR TEST ON BASIN. | |
| 12/10/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*/ 1) WEST MENS BAGGAGE RESTROOM 1212 WASTE AND VENT AIR TEST OK. WATER PIPING WATER TEST OK. UNISEX RESTROOM 1213 OK | |
| 08/19/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*/1) WASTE AND VENT SYSTEM IS OK. 2) OVERHEAD WATER DISTRIBUTION IS OK. 3) THIS INSPECTION IS FOR WEST WOMENS RESTROOM 1ST LEVEL ONLY. | |
| 05/23/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) THIS INSPECTION IS FOR CANOPY ROOF DRAINS ONLY AS INITIALIZED ON APPROVAL PLAN | |
| 05/02/2003 | PLUMBING - INTERMEDIATE | Partial Approval | 1.) OVERHEAD WATER DISTRIBUTION IS OK FOR CENTRAL BAGGAGE AREA AND EAST AREA ONLY. | |
| 04/17/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*THIS INSPECTION IS FOR RAIN LEADERS FROM EAST COLUMN #2 THRU COLUMN #22 WEST IS OK. 3.) 2" VENTS FOR FLOOR SINKS FOR AIR HANDLER IN RM #1326 AND MOP SINK IN RM #1209. 4.) OVERHEAD WATER DISTRIBUTION FROM RM# 1421, 1419, 1418,1420,1422, 1427.1 IS OK 2.) SOIL WATER TEST IS OK. |
|
| 04/01/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*COLUMNS Z T0 X LINES 1-2 6" RWL DOWN TO FLOOR OK. COLUMNS Z TO X LINES 7 -6" RWL DOWN TO FLOOR OK. COLUMNS Z T0 X LINES 16.4" RWL TO FLOOR OK. COLUMNS Z TO Y LINE 21 4" RWL TO FLOOR OK. WATER TEST ALL AREAS OK. |
|
| 03/25/2003 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*1.) AIR PRESSURE TEST FOR WASTE & VENT SYSTEM IN RESTROOM FOR BAGGAGE CLAIM. 2.) OK TO DRYWALL 3.) RAIN LEADER WATER TEST OK FROM GRID 1,3,5,7,16,18,20 ONLY. |
|
| 03/20/2003 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection 0000*MUST PROVIDE WATER TEST ON WASTE & VENT SYSTEM. |