Permit: T01CM00202

Parcel: 140420740


Addresses:

7250 S TUCSON BL


Inspection Status: Approved

Inspection History: BUILDING ABOVE CEILING

Permit Number - T01CM00202

Inspection Description - BUILDING ABOVE CEILING

Inspection Status - Approved

Date Description Inspector Results Comments
01/18/2005 BUILDING ABOVE CEILING Approved IVRS - Inspection :*
01/10/2005 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*PROGRESS @ LINK OK
12/17/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
12/14/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*REPAIR MONOKOTE ABOVE HARD LID AT EAST END OF LINK.
12/03/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
12/01/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/OK TO ROCK CEILINGS (HARD LILDS) IN WEST BAGGAGE
11/10/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
11/08/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
11/01/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/WEST FLYING ARCH READY FOR UNDERSIDE SHEATHING
10/20/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
10/19/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/ 1) OK TO ROCK HARD LIDS AND SOFFITS WEST SIDE BAGGAGE 2) OK TO START ROCKING AT EAST END OF WEST TICKET LEVEL SOFFIT AND HARD LID
10/14/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/OK TO COVER SOFFITS WEST BAGGAGE LEVEL
10/07/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :* WEST BAGGAGE AL PROGRESS OK. WEST TICKET SOFFIT SOUTH WALL & SUSPENDED ? @ EAST FRAME FOR LID UNDER FLY? ARCH OK
10/01/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*PARTIAL APPROVAL. PROGRESS AT WEST TICKET LEVEL FLYING ARCHES OK.
09/24/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/FIREPROOFING OF ROOF DECK @ LINK OK
09/21/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*PARTIAL APPROVAL. OK TO PLACE TILE EAST END.
09/17/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
08/26/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
08/19/2004 BUILDING ABOVE CEILING Not ready for Inspection IVRS - Inspection :* PATCH MONOKOTE
08/17/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/PARTIAL1)WEST (AREA B) TICKET LEVEL; MONOKOTE OK IN NEW AREARS. SOME REPAIR REQUIRED IN EXISTING AREAS 2)WEST BARREL ARCH PROGRESS OK, RECALL WHEN LAST 10 JOISTS ARE IN. 4)EAST BAGGAGE AREA STILL REQUIRES MONOKOTE REPAIR 5)OK TO TAPE ROCKED AREAS
08/10/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
07/21/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
07/02/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/ 1) FIRE PROOFING TOP AT WEST BARREL VAULT OK
06/21/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*
06/16/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/ 1) CFS FRAMING AT EAST BARREL ARCH CEILING OK TO COVER
06/04/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :* OK TO COVER SOFFITS EAST & BAGGAGE.
06/02/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :* MONOKOTS AREA E
05/21/2004 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection :*/ 1) HARD LIDS AND SOFFITS AREA E 5 1/2 BAGGAGE 2) OK TO START ROCKING
05/17/2004 BUILDING ABOVE CEILING Partial Approval SUSPENDED CEILING BAGGAGE LEVEL E AT DELTA OK 2) SUSPENDED CEILING BAGGAGE LEVEL E AT S.E. CORNER OK
09/24/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000*
09/17/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000*/1) ACCOUSTIC CEILING FOR THIS PHASE IS COMPLETE ON TICKET AND BAGGAGE LEVELS. 2) CORRUGATED STEEL UNDER CANOPY COMPLETE ONEAST 1/2.
09/15/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000* 1) CANOPY AREA AT TICKET LEVEL COMPLETE AND OK TO COVER. 2) WEST 1/2 TICKET LEVEL COMPLETE. 3) EAST 1/2 BAGGAGE LEVEL REQUIRES MINOR ADJUSTMENTS. a) GRID WIRE THAT SLOPES MORE THAN 1 IN 6 REQUIRES COUNTER SLOPE WIRE. b) PLEASE DO NOT USE GRID WIRES TO SUPPORT ELECTRIC OR DATA CABLES. USE SEPARATE HANGERS. c) FINISH REMOVING TEMPORY LIGHTING. d) OK TO INSTALL TILES.
09/12/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000* BAGGAGE AREA FROM ESCALATOR WEST
09/10/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000* OK IN CORRIDORS & OFFICES. LEAVE OUT TILES IN ROOMS NOT APPROVED ON 01045 SHEET ROCK
05/28/2003 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000*/ 1) SPRAY ON FIRE PROOFING WEST BARREL ARCH AREA
12/24/2002 BUILDING ABOVE CEILING Partial Approval IVRS - Inspection 0000*
1.) CAFCO SPRAY ON FIREPROOFING APPLIED TO STRUCTURAL STEEL @ A-B/1-7 TO DEPTH OF 1 1/2".