Date Description Inspector Results Comments
01/18/2005 FRAMING Approved 1) PLUMB, ELECT, MECH, NEED TO BE FINALED. 2) FIRE SPRINKLER FINAL 3) ALARM SYSTEM FINAL
12/30/2004 FRAMING Partial Approval IVRS - Inspection :* P LINK CEILING OK
12/22/2004 FRAMING Partial Approval IVRS - Inspection :*
1) NEED PANELS AT WEST END CANOPY
12/17/2004 FRAMING Partial Approval IVRS - Inspection :*
12/14/2004 FRAMING Partial Approval IVRS - Inspection :*LINK OK
12/03/2004 FRAMING Partial Approval IVRS - Inspection :*
12/01/2004 FRAMING Partial Approval IVRS - Inspection :*/SOFFITS & ALCOVES IN LINK OK
11/22/2004 FRAMING Partial Approval IVRS - Inspection :REPORTS OK IN KINK
HARD LIDS WEST BAGGAGE OK
YOU STILL NEED FIRESTOP @ SEVERAL SPRINKLER PIPE LOCATIONS
ALL PROGRESS OK EXTERIOR & INTERIOR
YOU NEED TO FINISH FIRESTOP @ SEVERAL SPRINKLER PIPE PENETRATIONS AND AT SOME EXISTING DAMAGED AREAS ALONG SOUTH EXTERIOR WALLS
I STILL NEED TO INSPECT INSIDE TUNNELS 1,2,7,8
11/10/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) OK TO COVER SOFFITS IN LINK 2) NICHES AT LINK OK
11/08/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) WEST TICKET COMPLETE
2) DO NOT COVER PASS THRU CEILING UNTIL FIRESTOP INSPECTED
11/01/2004 FRAMING Partial Approval IVRS - Inspection :*WEST BAGGAGE & TICKETING ESSENTIALLY COMPLETE
10/20/2004 FRAMING Partial Approval IVRS - Inspection :*
10/19/2004 FRAMING Partial Approval IVRS - Inspection :*
10/18/2004 FRAMING Partial Approval IVRS - Inspection :ALL PROGRESS OK
10/14/2004 FRAMING Partial Approval IVRS - Inspection :*/ALL PROGRESS OK. REPAIR MONOKOTE TYEKET? LEVEL WEST END BEFORE COVERING SOFFITS
10/07/2004 FRAMING Partial Approval IVRS - Inspection :* WEST TICKET WEST WALL & STRUCTURAL STEEL AWNING @ WEST
10/01/2004 FRAMING Partial Approval IVRS - Inspection :*PARTIAL APPROVAL. ALL PROGRESS WEST T & B OK.
09/21/2004 FRAMING Partial Approval IVRS - Inspection :*PARTIAL APPROVAL. WEST AREA PROGRESS OK.
09/15/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) ALL C.F.S. PROGRESS IN WEST AREA OK 2) SOUTH WALLS EAST VAULT OK 3) SOUTH EXTERIOR SHEATHING AT LINK OK
09/10/2004 FRAMING Partial Approval PROGRESS WEST BAGGAGE OK CFS FRAMING, ?? AND SOFFITS IN LINK OK
09/07/2004 FRAMING Partial Approval IVRS - Inspection :*/
01035-1) ALL PROGRESS WEST BAGGAGE AREA OK (SOFHTS?, LIDS, WALLS ETC.)
2)PROGRESS WEST TICKET LEVEL ON SEFHTS? & PARNPETS? OK
3)HARD LID @ EAST FLYING ARCH OK (AND PARAFET? RETURN)
4)HARD LID @ HIGH LINK OK (EAST OF BARRELARCH)
5)PAMPETS @ LINK AREA OK (REPAIR WHERE DAMAGED BY ROOFERS)
08/31/2004 FRAMING Partial Approval IVRS - Inspection :*
08/30/2004 FRAMING Partial Approval IVRS - Inspection :*
08/26/2004 FRAMING Partial Approval IVRS - Inspection :*
08/24/2004 FRAMING Partial Approval IVRS - Inspection :*/PARTIAL SOUTH WALL & PARAPETS? LINK OK
1045-PARTIAL-PROGRESSED-TECKET LEVEL E
01015-UPPER PEDESTRIAN RAMP @ LINK OK
01030-FLAT ROOF OVER LINK OK
08/19/2004 FRAMING Partial Approval IVRS - Inspection :* BARREL ARCH AREA B
08/17/2004 FRAMING Partial Approval IVRS - Inspection :*
08/16/2004 FRAMING Partial Approval IVRS - Inspection :*
08/12/2004 FRAMING Partial Approval IVRS - Inspection :*/1)AREA B BAGGAGE PROGRESS OK WALLS, CIELINGS, COLUMNS, SUFFITS, ETC. 2)REPAIR MONOKOTE ON COLUMNS & BEAMS AND RECALL INSPECTION BEFORE COVERING. 3)C.F.S. LIDS, SOFTLIS ETS. OK AREA E TICKET LEVEL DO NOT COVER WHERE MONOKOTE REQUIRES REPAIR UNTIL REPAIRS HAVE BEEN INSPECTED. 4) CIELING EASTEND AREA E BAGGAGE SITLL NOT READY 5) MONOKOTE DAMAGE AREA E BAGGAGE STILL NOT REPAIRED
PLEASE MAKE MONOKOTE REPAIRE AT BAGGAGE LEVEL BEFORE CONTINUING.
08/10/2004 FRAMING Partial Approval IVRS - Inspection :*
08/05/2004 FRAMING Partial Approval IVRS - Inspection :*
07/27/2004 FRAMING Partial Approval IVRS - Inspection :*
07/21/2004 FRAMING Partial Approval IVRS - Inspection :ALL C.F.S. PROGRESS AREA E BAGGAGE LEVEL OK
OK TO COVER WALLS, SOFFITS, HARD LIDS AS COMPLETED
07/13/2004 FRAMING Partial Approval IVRS - Inspection :*
06/29/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) FRAME PROGRESS AREA B BAGGAGE OK FOR CEILINGS, SOFFITS AND WALLS 2) SOUTH SIDE OF WEST BARREL ARCH OK AT LOW ROOF
06/24/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) EAST TICKET KNIFE WALL
06/21/2004 FRAMING Partial Approval IVRS - Inspection :*
06/02/2004 FRAMING Partial Approval IVRS - Inspection :* SOFFIT FRAMING E ELEV SHAFT ROOF- HEAVY STRUCTURAL VARIOUS AREAS. PROGRESS WITH C.F.S. & SHEET ROCK IS OK
05/25/2004 FRAMING Partial Approval IVRS - Inspection :*
05/21/2004 FRAMING Partial Approval IVRS - Inspection :*
05/17/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) TO PROGRESS AREA E BAGGAGE LEVEL OK
05/05/2004 FRAMING Partial Approval IVRS - Inspection :*/ 1) PROGRESS ON C.F.S. PARAPETS OK 2) PROGRESS ON STRUCTUAL STEEL AREA E OK
04/21/2004 FRAMING Partial Approval IVRS - Inspection 0000* 1) PROGRESS ON STRUCT STEEL AREA E OK. 2) PROGRESS LUGGAGE LEVEL CFS AREA E OK
04/14/2004 FRAMING Partial Approval IVRS - Inspection 0000* EAST BAGGAGE AREA OFFICE OK.
03/16/2004 FRAMING Partial Approval IVRS - Inspection 0000* CEILING FRAME TICKET LEVEL BY WEST ESCALATOR
03/10/2004 FRAMING Partial Approval IVRS - Inspection 0000* SOFFIT TICKET LEVEL BY FRONTIER AIRLINES OK
03/02/2004 FRAMING Partial Approval IVRS - Inspection 0000* REAR BAGGAGE AREA EAST END
02/26/2004 FRAMING Partial Approval IVRS - Inspection 0000* 1) COLD FORM STEEL FRAMING OK INSIDE BAGGAGE LEVELS. 2) DO NOT COVER!!! UNTIL I SEE MONOKOTE REPAIRS.
12/11/2003 FRAMING Partial Approval IVRS - Inspection 0000* MEN'S & FAMILY RESTROOMS LIDS OK
12/10/2003 FRAMING Partial Approval IVRS - Inspection 0000* LIGHT GAUGE STEEL FRAMING OK FOR MENS AND FAMILY RESTROOM AREA BY TUNNEL 2 OK.
09/30/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) 2 HR CENTRAL BAGGED SIDE OK
09/26/2003 FRAMING Partial Approval IVRS - Inspection 0000*/1) FIRE STOP 2 HOUR BAGGAGE AND INSIDE TUNNEL. 2) SUPPLY TEST RESULTS FOR FIRE BARRIER ETC. 3) ADA SIGNAGE READILY VISIBLE.
07/21/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) CONTINUED PROGRESS ON LIGHT GAUGE FRAMING ON BAGGAGE AND TICKETING LEVELS. GENERALLY OK, NO DEFICIENCIES NOTED
07/15/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) SUSPENDED CEILING BAGGAGE AREA COMPLETE
07/11/2003 FRAMING Not ready for Inspection IVRS - Inspection 0000*
07/02/2003 FRAMING Not ready for Inspection IVRS - Inspection 0000*
06/26/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) PROGRESS "FRONT OF STONE" BAGGAGE LEVEL
06/25/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) SOUTH WALL LINK AREA 2) SOFFIT FRAMING BAGGAGE AREA
06/18/2003 FRAMING Partial Approval 1) SUB ROOF FRAMING CENTRAL BAGGAGE-OK
06/10/2003 FRAMING Partial Approval IVRS - Inspection 0000*/ 1) PROGRESS IN BAGGAGE LEVEL FRAMING A) DO NOT COVER HARD LID IN CORRIDOR UNTIL FIRE STOP INSPECTION HAS BEEN COMPLETED BY CITY OF TUCSON (MYSELF) B) PRVOIDE ARCHITECT STAMPED RFI FOR SUSPENDING HARD LID IN CORRIDOR. (WIRE SUSPENSION AT LEADING EDGE DUE TO CONDUIT BLOCKING STUDS FROM BEING ATTACHED A CEILING 2) WINDOW WALL AT TICKET LEVEL OK 3) SOFFITS COMPLETE AROUND EAST BARREL ARCH 4) CEILING IN WEDGE (DELTA) OK 5) CEILING IN WEST BARREL ARCH OK 6) HIGH SOUTH SOFFIT AND NORTH SOFFIT AROUND WEST BARREL ARCH OK
05/12/2003 FRAMING Partial Approval IVRS - Inspection 0000*DECK WELDS & STRUCTURAL STEEL @ LINE AREA APPEAR OK I STILL NEED SPEC INSP ON STRUCTURAL WELDS.
05/06/2003 FRAMING Partial Approval IVRS - Inspection 0000*INSPECTED VARIOUS AREAS TICKET AND BAGGAGE LEVEL NON STRUCTURAL FRAMING
2.) HIGH CIELING INSIDE TERMINAL OK
04/25/2003 FRAMING Partial Approval IVRS - Inspection 0000*PARTIAL
1.) MONOKOTE ON STRUCTURAL STEEL IN WEST BARREL ARCH OK
I STILL NEED TO SEE SPECIAL INSP. REPORT FROM TERRACON.
04/23/2003 FRAMING Partial Approval IVRS - Inspection 0000*PRELIMARY INSP DECK & STRUCT. FRAME @ CANOPY.
04/22/2003 FRAMING Partial Approval IVRS - Inspection 0000*C1 TO D/110-111. CEILING BAGGAGE LEVEL 22-24/B-C
04/11/2003 FRAMING Partial Approval IVRS - Inspection 0000*FIRE @ HIGH BARREL ARCH AREA D.
2.) MONOKOTE REPAIR COMPLETE @ BAGGAGE LEVEL 21-25/B1-C1.
3.) RFI FOR W16 BEAM TO EMBED REPAIRS REVIEWED (RFI 244-249) REPAIR OK
04/10/2003 FRAMING Partial Approval IVRS - Inspection 0000*
03/31/2003 FRAMING Partial Approval IVRS - Inspection 0000*1.) FRAMING EAST AREA BAGGAGE LEVEL RESTROOM OK
2.) DO NOT COVER UNTIL. SPRAY ON FIRE SAFING HAS BEEN REPAIRED AND I HAVE INSPECTED IT.
03/26/2003 FRAMING Partial Approval IVRS - Inspection 0000*MET WITH JERRY D. NUNZIO AWS CERTIFIED SPECIAL INSPECTOR FOR TERRACON. WE WENT OVER HIS INSPECTION FOR AREA D, 16-22/Y-2.
MEETING WAS SET BECAUSE SPECIAL INSP. REPORTS IN SUNDTS OFFICE FROM TERRACON DO NOT GIVE CORRECT LOCATIONS OF MR DE NUNZIOS' INSPECTIONS
2.) PERM OUR MEETING WELDING HAS BEEN ACCEPTED IN ABOVE AREA. NO BOLTING INSPECTIONS HAVE BEEN PERFORMED.
03/17/2003 FRAMING Partial Approval 1.) HEAVY STEEL AREA C NEARLY COMPLETE.
2.) HIGH DELTA @ Y-2/7-11 IN PROGRESS.
3.) I NEED TO SEE RFI FOR STEEL FABRICATED TOO SHORT.