Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T01BU03302
Inspection Description - GRADING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2006 | GRADING - FINAL | Approved | ||
| 12/09/2004 | GRADING - FINAL | Denied | SEE PREVIOUS COMMENTS AS FOLLOWS: BASIN A - COMMENTS #1, #2, & #4 BASIN B - COMMENTS #2 & #3 |
|
| 10/25/2002 | GRADING - FINAL | Denied | FINAL GRADING NOT APPROVED. SEE COMMENTS NOTED FOR INSPECTION ON 8-21-02, WITH THE EXCEPTION OF THOSE ITEMS ALREADY COMPLETED FOR: "BASIN A" NOTES 2 & 3, AND "SITE" NOTES 1 & 2. PLEASE ADDRESS THE REMAINING ISSUES BEFORE THE NEXT INSPECTION. |
|
| 08/21/2002 | GRADING - FINAL | Denied | BASIN A 1) DEPTH EXCEEDS 3 FEET AND THE SLOPE RATIOS ARE LESS THAN 4:1 AS SHOWN ON THE APPROVED PLANS. AS NOTED IN OUR STORMWATER DETENTION/RETENTION MANUAL SECTION 3.6.2 THIS WILL REQUIRE A 42 INCH SAFETY BARRIER. THE 42 INCH SAFETY BARRIER IS TO BE PLACED AROUND THE PERIMETER OF THIS BASIN AT THE TOP OF THE SLOPE. 2) ACCESS RAMP IS CURRENTLY BEING BLOCKED BY THE HANDICAP PARKING SIGN. THIS SIGN WILL NEED EITHER TO BE RELOCATED, OR INSTALLED IN A MANNER SO THAT IT CAN BE REMOVED DURING MAINTENANCE. 3) DAMAGED ASPHALT HAS BEEN NOTED NEAR THE INLET INTO THE BASIN. ADDITIONAL CURB CUTS HAVE BEEN MADE ADJACENT TO THE INLET, THESE NEED TO BE REPAIRED AND CLOSED TO PREVENT EROSION. 4) EROSION HAS BEEN NOTED AROUND THE OUTER PERIMETERS OF THE BASIN, CAUSING ADDITIONAL SOILS TO BE DEPOSITED INTO THE BASIN. THIS MATERIAL NEEDS TO BE REMOVED FROM WITHIN THE BASIN, AND ALL SLOPES NEED TO BE STABALIZED. BASIN B 1) AN UNUSED CURB CUT LOCATED ON KOLB NEEDS TO BE CLOSED UP. THIS DIRECTIVE IS NOTED ON THE STAMPED SET OF THE APPROVED PLANS. 2) THE DEPTH OF THE BASIN EXCEEDS 2 FEET AND THE SLOPES ARE LESS THAN 4:1. AS NOTED IN OUR STORMWATER DETENTION/RETENTION MANUAL SECTION 3.6.2 THIS WILL REQUIRE A 42 INCH SAFETY BARRIER. THE 42 INCH BARRIER IS TO BE PLACED AROUND THE PERIMETER OF THE BASIN AT THE TOP OF THE SLOPE. 3) EROSION HAS BEEN NOTED ALONG SOME OF THE SLOPES AND WILL NEED TO BE REPAIRED. SITE 1) THE WALL OPENINGS ALONG WEST PERIMETER DO NOT HAVE ROCK RIPRAP PLACED OUTSIDE OF THE PERIMETER WALL. ADDITIONAL MATERIAL IS SHOWN TO BE PLACED ON FILTER FABRIC BETWEEN THE PERIMETER WALL AND THE PROPERTY LINE. 2) REMOVE ALL CONSTRUCTION TRASH AND DEBRIS FROM ALL DRAINAGE WAYS AND BASINS. 3) THE ROOF DRAINAGE HAS BEEN NOTED DURING THE PREVIOUS RAINS TO SPILL OUT ONTO THE SIDEWALKS. THIS WATER NEEDS TO BE DIRECTED INTO THE SIDEWALK SCUPPERS SO THAT IT PASSES UNDERNEATH THE SIDEWALKS. ON THIS SITE IT HAS BEEN NOTED THAT THE 15 & 30 FOOT WATER EASEMENT FALLS WITHIN THE FOOT PRINT OF THE NEW BUILDINGS. THIS IS A NO BUILD EASEMENT AND WILL CREATE SOME ADDITIONAL PROBLEMS FOR THIS SITE. THE FINAL RELEASE FOR THIS SITE CAN NOT BE GIVEN UNTIL ALL THE DRAINAGE ITEMS ARE COMPLETE. THIS WILL REQUIRE THAT THE SITE IS TO BE REINPECTED ONCE ALL OF THE BUILDINGS ARE COMPLETE. |
|
| 07/10/2002 | GRADING - FINAL | Denied | PROGRESS INSPECTION REQUESTED FOR THIS SITE. ALL DRAINAGE WORK NEEDS TO BE COMPLETED PRIOR TO SCHEDULING A RE-INSPECTION. |