Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/17/2003 | GRADING - FINAL | Approved | ||
| 03/26/2003 | GRADING - FINAL | Partial Approval | COMPLETE ITEMS #3 AND #7 FROM THE PREVIOUS INSPECTION DATED 12/12/2002 | |
| 12/12/2002 | GRADING - FINAL | Denied | 1. Provide Bicycle parking as specified in the approved plans. 2. Provide drainage for roof drain water without conveying over sidewalk/handicap ramp. 3. Construct 5 ft CMU wall at west propery line. 4. Provide drainage through 5 ft CMU wall at north propery line as specified in the plan. 5. Embed wings of outlet weirs in soil. 6. Fix erosion damage in side slopes of retention basin. 7. Provide drawings and calculations showing revised retention basin to demonstrate that retention and drainage requirements are met. |