Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 09/20/2001 |
ELECTRIC - UNDERGROUND |
|
Approved |
|
| 08/31/2001 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
IVRS - Inspection 0000*1.) NEED LETTER OF COMPLIANCE W/TORQUING REQUIREMENT FROM/LICENSED L-11 CONTRACTOR 2.) POST BOND AND NEED TO COMPLETE SIGN OFF SHEET FOR TEMP POWER TEST AND OR C OF O 3.) ADDRESS SERVICE 4.) BOLT DAWN SERVICE SWITCHGEAR. |
| 08/10/2001 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
IVRS - Inspection 0000*2 PARALLED 4" CONDUIT FROM TRANSFORMER TO NEW SERVICE ENTRANCE LOCATION. REV. #11 APPROVED. |
| 05/15/2001 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
IVRS - Inspection 0000* 2 1/2 " CONDUIT UNDER GROUND FROM ELECTRICAL SERVICE TO PANEL A |