Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/25/2015 |
ENGINEERING - FINAL |
|
Approved |
|
| 03/29/2002 |
ENGINEERING - FINAL |
|
Denied |
TEMPORARY C OF O APPROVED AT THIS TIME COMPLETE THE FOLLOWING ITEMS PRIOR TO RESCHEDULING A RE-INSPECTION: 1) INSTALL THE 6-INCH CURB AS SHOWN ON THE APPROVED PLANS. 2)THE ONSITE SIDEWALK DOES NOT CONNECT INTO THE SIDEWALK IN THE RIGHT-OF-WAY, COMPLETE THIS WORK. 3) INSTALL THE 6-FOOT CMU WALLS AS SHOWN ON THE APPROVED PLANS W/WEEPHOLES. 4) THE 10-FOOT SETBACK DIMENSION ON THE EAST SIDE OF THE DEVELOPMENT HAS BEEN REDUCED, HAS THIS BEEN APPROVED BY THE ZONING DEPARTMENT. 5) CONSTRUCT THE TRASH ENCLOSURE AS SHOWN ON THE APPROVED PLANS. |