Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/19/2001 | ELECTRIC - FINAL | Approved | IVRS - Inspection 0000* | |
| 04/13/2001 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection 0000*PARTIAL, OK TO USE CONPRESSORS. RECEIVED LETTER FROM ENGINEER. NOTE: FOR A FINAL MAINDISCONNECT MUST BE PERMANENTLY LABLED. | |
| 03/05/2001 | ELECTRIC - FINAL | Partial Approval | IVRS - Inspection 0000* ALL WORK COMPLETE - FINAL SUBJECT TO THIRD PARTY VERIFYCATION OF COMPRESSORS | |
| 02/28/2001 | ELECTRIC - FINAL | Denied | TALKED TO ELECTRICAL CONTRACTOR JOE (CORONA ELEC.) SAID MAIN 200AMP SWITCH HAD NOT BEEN RELOCATED, NO OTHER CORRECTIONS MADE, IN FACT STATED THAT SUNDANCE DESIGN HAD NOT CONTACTED THEM ON A CALL IN FOR REINSP. HE SAID ITEMS WOULD BE COMPLETED TODAY AND INSP. WOULD BE RECALLED FOR TEC | |
| 02/27/2001 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection 0000* | |
| 02/23/2001 | ELECTRIC - FINAL | Denied | IVRS - Inspection 0999* NO PLANS ON SITE | |
| 02/23/2001 | ELECTRIC - FINAL | Denied | IVRS - Inspection 0999* 1) ID PANEL ( OUTSIDE ) SCRAPE GROUND CONNECTION LUG 2) SCHEDULE PNC CP7 ( ID OUTSIDE) 3) MAIN SWITCH REQUIRES 3' IN FRONT OF, ID DISCONNACT AND SUPPORT 1 1/2 CONDUIT WITH 3' OF SWITCH 4) S.SIDE UNIT ID PHASES CONDUCTORS IN CONTROLLER 5) ID COMPRESSOR SW'S COMPRESSORS NOT LISTED 6) SCRAPE BEHIND LUGS ON COMPRESSOR SW'S AND CONNECT |
|
| 12/06/2000 | ELECTRIC - FINAL | Not ready for Inspection | CONTRACTOR DID NOT CALL |