08/16/2001 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection 0000*1.) FINAL SET OF 3 ROOF DRAINS ON NORTH SIDE OK WATER TEST OK 2.) ADD HANGERS AS NEEDED WILL CHECK ON FINAL. 3.) GENERAL INDUSTRIAL WASTE ADD HANGERS AS NEEDED 4' MAX HORIZONTAL FOR ABS WILL CHECK ON FINAL. | |
08/12/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*1.) SEVIVNERS NOTES ON APPENDIX D APPROVED CONTINING ROOF DRAIN AND OVERFLOW UNDER APPLICABLE CODES ROOF DRAINS AND OVERFLOWS CONTINED APPROVED. 2.) WATER TEST ON THREE REMAINING SOUTH SIDE DRAINS OK OK TO DROP TEST. 3.) ABS TO BE SUPPORTED MAX EVERY FOUR FEET HORIZONTALLY ADD HANGERS AS REQUIRED. | |
08/08/2001 | PLUMBING - INTERMEDIATE | Partial Approval | 1.) 2 ROOF DRAINS AND OVERFLOWS IN ADMIN BLDG OK WATER TEST OK OK TO COVER 2.) INTERMEDIATE AT BREAKROOM OK OK TO COVER 3.) SHOWERS AND VALVES OK OK TO COVER 4.) HAVE ENGINEER FAX AUTHORITY TO COMBINE ROOF DRAIN AND OVERFLOW DRAINS TO CONTRACTOR I AM UNABLE TO FIND THIS IN MY 94 MODIFICATION. | |
08/07/2001 | PLUMBING - INTERMEDIATE | Partial Approval | 1.) ROOF DRAIN & OVERFLOW COMBINED APPROVED UNDER DATE OF ISSUE OF PERMIT 2.) CLASSROOM ONE, TWO, AND THREE, LIBRARY ROOF DRAINS AIR OVERFLOW OK WATER TEST OK 3.) GAS PRESSURE TEST 30LBS OK. | |
08/05/2001 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection 0999* | |
07/26/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*SIGNED OFF FOR TEMP POWER | |
07/25/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*1.) GAS NOT QUITE READY 2.) ROOF DRAINS TO BE SCHEDULED. | |
06/19/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*1.) WATERTEST ON ABS IN BATHROOMS OK. 2.) CLEAN OUT EXTENSION OK 3.) OK TO COVER WALLS IN BATHROOMS | |
06/13/2001 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection 0999*1. NO WATER TEST ON ABS 2. CLEAN-OUT EXTENSIONS SHALL BE CONNECTED TO VERTICAL PIPING WITH A WYE BRANCH FITTING OR EQUIVALENT SWEEP 3. PLEASE DO NOT INSULATE HOT WATER UNITL AFTER INSPECTION 4. COMPLETE VENTING OF EWC, FLOOR SINK, SINK 5. SHOWERS & VALVES NOT COMPLETE 6. WATER PRESSURE TEST, LINE PRESSURE ONLY 7 PLEASE CHECK INDICATE WASTE REQUIREMENT. | |
06/05/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*1)ALL EYE WASHES ALONG COLUMNS C AND D OK.1 1/2" SUPPLY TO BOOTHS IN WALL OK.2)OK TO COVER THESE ITEMS ONLY. | |
03/07/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000* 1) N/H PIPE WRAPPED 2) FLOOR DRAINS AND SINKS SET 3) OK BY ME TO POUR | |
02/01/2001 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000* BLDG DRAIN FROM INSIDE BLDG TO BLDG SEWER OK WATER TEST OK OK TO COVER 4" AREA DRAINS (3) OK WATER TEST OK OK TO COVER |