Inspection Status: Partial Approval
Inspection History: ROOF NAILING
| Date |
Description |
Inspector |
Results |
Comments |
| 11/06/2000 |
ROOF NAILING |
|
Partial Approval |
CONTRACTOR WANTING TO DRY IN ROOF. THERE ARE SEVERAL PLANS REVISIONS STILL PENDING. CONTRACTOR CONTINUE AT OWN RISK PENDING APPROVED REVISIONS AND TRUSS CALC'S |
| 10/17/2000 |
ROOF NAILING |
|
Partial Approval |
IVRS - Inspection 0000*/1. SHEATHIN REQUIRED AT GABLE ENDS IF AS BUILT STRUCTURE ISN'T MODIFIED. 2. INSTALL RIDGE BLOCKS NAIL THRU ROOF SHEATHIN. 3. PROVIDE PREVIOUS INSPECTION RESULTS. 4. PROVIDE APPROVED REVISION FOR I BEAM INSTALLATION BEARING ALL SCISSOR TRUSSES. 5. COMPLETE ALL TRADES BEFORE FRAMING INSPECTION. |
| 08/29/2000 |
ROOF NAILING |
|
Denied |
1. COMPLETE BIRD BLOCKING (SHEET AND DETAIL 1 AND 3). 2. COMPLETE RIDGE BLOCKING PER PLAN. 3. PROVIDE "X" BRACING AT BOTH ENDS AND AT 25'-0' O.C. 4. CLIP FULL BEARING GABLE END TRUSSES. 5. FLAT BLOCK OVER SPACED ROOF SHEATING. 6. PROVIDE APPROVED TRUSS CALC'S. 7. PROVIDE REVISION FOR CARPORT I BEAM STEEL WITH DETAILS FOR HOLDDOWNS AND UPLIFT BOLTS. 8. COMPLETE ROOF NAILING. NOTE: PROVIDE PAST INSPECTION RESULTS. |