Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T00CM03580

Parcel: 103080120

Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T00CM03580

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
05/21/2001 FRAMING Approved IVRS - Inspection 0000*
12/26/2000 FRAMING Denied IVRS - Inspection 0999*/1. DBL TJI NEED TO BE SOLIA MEMBER PROVIDE WEB STIFFERNERS. 2. CHECK RED HEADS THRU OUT. 3. PROVIDE HANGERS AT PORCH RAFTER TO LEDGER CONNECTION. 4. WATER CLOSET SHOULD BE 15" AWAY FROM ANY WALL.
12/20/2000 FRAMING Denied IVRS - Inspection 0999*/1. CLEARANCE FOR WATER CLOSET NOT PROVIDED NEED 15" SIDE CLEARANCE MEASURED FROM CENTER OF FIXTURE BOTH SIDES BEHIND GARAGE. 2. PROVIDE PIG TAIL GROUNDS FOR ALL SNAP SWITCHES. 3. LOW VOLTS CANNOT BE IN HIGH VOLT BOXES CLOSET AREA BEHIND GARAGE. 4. PLUMBING NOT COMPLETE ITEMS FROM PREVIOUS INSPECTION NOT COMPLETE. 5. HORIZONTAL VENT CAN'T BE RUN UNITL 6" ABOVE FLOOD RIM FOR FIXTURE INTENDED. 7. POSITIVE CONNECTION REQUIRED AT ALL POST TO BEAM. 8. COMPLETE EXTERIOR BRACED PANELS. 9. REINSPECTION WILL BE IMPOSED IF INSP. IS CALLED PRE MATURE.
12/15/2000 FRAMING Partial Approval IVRS - Inspection 0000*/1. ITEM #4 ABOVE NOT PER PLAN. 2. LEDGER CONNECTIONS NOT PER PLAN S31 9.
12/07/2000 FRAMING Denied IVRS - Inspection 0999*/1. PROVIDE NAIL PROTECTION ON BORED HOLES IN STUDS FOR PLUMBING AND ELECTRICAL RUNS CHECK THRU OUT. 2. PROVIDE REVISIONS FOR 2 WINDOWS AT GARAGE. 3. BLOCK ALL MECH., REG. 3 SIDES. 4. BLOCK TJI'S AT STUDY AND MAST. BDRM BEARING WALL AS PER PLAN DETAIL 11 S3.1 AND AT ENTRY. 5. CANNOT NAIL INTO TJI'S BOTTOM CHORD PER MANUFACTURES SPECS AT STUDY. 6. SECURE BOTTOM PLATES TO FLOOR THRU OUT. 7. STRAP BEAMS AS PER PLAN DETAIL 12 S3.1. 8. PROVIDE FIRE STOPS AT ANY COLUMN AT LOWEST CEILING POINT. 9. PLAN CALLS FOR 2 X 10 NAILERS TO STUD WALL DETAIL 10 S3.1. 10. COMPLETE FRAMING FOR SGD AT PATIO. 11. PROVIDE SUPPORT AT VALLEY RAFTER AT PATIO.